E/25/57 Procurement of Electrical Rewire Contract

Decided Executive 2 papers

AI summaryIpswich Borough Council Executive has approved the procurement of a 12-month electrical rewire contract to rewire 59 General Needs flat blocks, delegating award of the contract to officers within existing capital budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOpen tender under Procurement Act 2023 for 12-month rewire contract
MoneyWithin existing capital budgetHRA capital programme, detailed in Exempt Appendix 2
What happens nextNot stated
Who it affectsTenants and leaseholders in 59 flat blocks301 blocks tested in 2025, 59 need full rewire

What was decided

The Executive authorised the Assistant Director for Housing, in consultation with the Section 151 Officer, Head of Legal Services and Head of Procurement, to progress with the procurement of an electrical rewire contract. Report 14.1, P59

The Executive delegated authority to the Assistant Director of Housing, in consultation with the Housing and Resources Portfolio Holders, Head of Finance, Head of Legal and Head of Procurement, to award a 12-month contract provided it is within the capital budget in Exempt Appendix 2. Report P61

The Executive authorised the Assistant Director for Housing to commence statutory leaseholder consultation under the Landlord and Tenants Act 1985 and the Service Charge (Consultation Requirements) (England) Regulations 2003. Report 14.3, P66

Why

Every 5 years the Council must carry out electrical installation condition reports on its systems. Testing in 2025 identified 59 General Needs flat blocks needing a full rewire, so the Council needs a compliant contractor to maintain safe landlord supplies in communal areas. Report 2.1, 2.2, P6

The procurement aims to secure a cost effective, quality driven solution, meet legislative requirements such as British Standards and the Building Safety Act, and obtain value for money through a mix of price and quality. Report P6, 2.8

Delegating the award to officers is intended to allow the Council to enter into contracts quickly, reducing the risk of backlogs in the rewire programme. Report P61

What happens next

Run an open procedure procurement under the Procurement Act 2023, publishing contract notices on Suffolk Sourcing and Find a Tender, and assess bidders on financial and technical capability. Report 2.7, 2.8

Evaluate tenders on a 60% price and 40% quality basis, with moderation led by the Procurement Team, to identify the most economically advantageous tender. Report 2.8

Commence statutory leaseholder consultation in line with sections 20 and 20ZA of the Landlord and Tenants Act 1985, and report back to Executive to consider any responses before appointment. Report 5.1, 11.3, 14.3

Options considered

  • Chosen: Tender the electrical rewire contract using an open tender process (Procurement Act 2023 open procedure). Likely to generate strong interest, including from local companies, and produce an economically advantageous tender Report P19, 4.1, P21
  • Rejected: Use a National Framework Agreement. Frameworks generally exclude local SMEs, suppliers cannot apply once it is set up, and the Council has less control over terms Report P22, 4.2, P24
  • Rejected: Reserve contract award to Executive and receive a further report before deciding. Executive chose to delegate award to officers to avoid delays Report P62, P63, P64

Implications

  • Legal: Procurement will follow the Procurement Act 2023 open procedure, and leaseholders must be consulted under sections 20 and 20ZA of the Landlord and Tenants Act 1985 and the 2003 Service Charge Regulations before a long-term qualifying contract is awarded. Report 5.1, 11.1, 11.3
  • Financial: The rewire programme is funded through the HRA Capital Programme within the Medium Term Financial Plan and the HRA 30-year Business Plan; the budget is lower than originally expected because only 59 of 301 tested blocks need full rewiring. Report 2.3, 10.1, 10.2, 10.3
  • Equalities: An Equalities Impact Assessment found no equality issues, and the tender evaluation will check that bidders have robust equal opportunities policies and procedures. Report 8.1, 8.2, 8.3, 8.5
  • Climate: The successful contractor will be encouraged to develop an environmental plan, use electric vehicles where possible, reduce fuel use, and install efficient replacement systems, although the report itself is judged to have no direct climate impact. Report 7.1, 7.2, 7.3, P15
  • Risk: Risks identified include contractor failure, supply chain issues, sub-standard materials, faulty installation and Health and Safety failures, with mitigations such as supply chain vetting, novation or re-tender, qualified electrician checks and audited health and safety processes. Report P27

Who and where

  • Tenants of the 59 General Needs flat blocks identified as needing a full rewire Report 2.2, P14
  • Leaseholders in the 59 General Needs flat blocks, who will be formally consulted under the Landlord and Tenants Act 1985 Report 5.1, 14.3
  • Local companies and small and medium enterprises (SMEs) being encouraged to bid through the open tender Report 2.9, P10
  • The Council's Housing Revenue Account, as the programme is funded from the HRA capital programme Report 2.3, 10.1

Timeline

  • 2025: 301 General Needs flat blocks tested under the 5-year electrical installation condition report cycle; 59 identified as needing full rewiring Report 2.1, 2.2
  • 2026/27: Proposed capital budget provides for the start of the full communal rewire programme Report 10.2
  • 12 months (contract term): Length of the new electrical rewire contract to be procured Report 2.4, P61

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing
  • MTFP: Medium Term Financial Plan, the Council's multi-year financial planning document
  • PA23: Procurement Act 2023, the legislation governing how the Council runs competitive procurements
  • SME: Small and medium sized enterprises
  • EIA: Equalities Impact Assessment, an assessment of how a proposal may affect people with protected characteristics
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item124

Resolved

a) That Executive authorises the Assistant Director for Housing, in consultation with the Section 151 Officer, Head of Legal Services and Head of Procurement, to progress with the procurement of an electrical rewire contract. Reason: To enable bids to be received and evaluated from appropriate contractors. Subject to a), that Executive: b) Authorises the Officer(s) with delegated authority, Assistant Director of Housing, in consultation with the Housing Portfolio Holder, Resources Portfolio Holder, Head of Finance, Head of Legal and Head of Procurement, to award an electrical rewire contract for a 12-month term provided it is within the capital budget contained in Exempt Appendix 2 to the report. Reason: To enable the Council to enter into contracts which provide value for money, with successful providers who are capable of meeting the Council’s requirements and so are the most advantageous to the Council. This will minimise the risk of any backlogs if contracts can be awarded as quickly as possible. c) Authorises the Assistant Director for Housing to commence statutory leaseholder consultation in accordance with the Landlord and Tenants act 1985 (as amended) and the Service Charge (Consultation Requirements) (England) Regulations 2003. Reason: To first inform leaseholders of the Council’s intention to enter into a long-term qualifying contract and then to inform them of the decision to appoint a contractor.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

Background

2.1Every 5 years, the Council is required to undertake an electrical installation condition report for all its electrical systems. This includes the landlord’s supplies in the communal areas of General Needs flat blocks.

2.2Of the 301 General Needs flat blocks tested in 2025, 59 blocks have been identified as needing a full electrical rewire due to their age and condition. The rewire work will also address the emergency lighting on the stairs and escape routes.

2.3The current budget provision for this planned electrical wiring replacement has been previously approved and is included in the Housing Revenue Account Capital Programme as part of the Council’s Medium Term Financial Plan.

2.4The term for the contract will be 12 months. The Council’s current electrical specification has been updated and will be used for this procurement.

2.5The objectives of the procurement are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E-25-57 Appendix 1: EQIAAppendix 28 KB Download
PDF
E/25/57 Procurement of Electrical Rewire ContractReport 356 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
NM
Councillor Neil MacDonaldLeader, present
BR
Councillor Bryony RudkinDeputy Leader, present
JC
Councillor John CookCommittee Member, present
MC
Councillor Martin CookCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
JR
Councillor Jane RileyCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, present
LT
Councillor Lucy TrenchardCommittee Member, present
IF
Councillor Ian FisherCommittee Member, present

On this subject at Ipswich

Search all
  1. E/25/57 Procurement of Electrical Rewire ContractThis decision
  2. E/23/56 IP City Mechanical & Electrical (M&E): Main Contractor Procurement and Planning StrategyDecided
  3. E/22/42 IP-City Centre Mechanical & Electrical (M&E) Main Contractor ProcurementDecided

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies