London Borough of Islington
Executive, Thursday 18 July 2024 at 7.00pm

Finsbury Leisure Centre Redevelopment

Noted Executive 5 papers

Executive noted this item on Thursday 18 July 2024. Below is the council's own wording, with the papers it was decided on.

Item255

Resolved

RECOMMENDATIONS: Subject to ongoing gateway reports and financial viability assessments, to: 2.1 Note the increased project cost since Stage 2 and the project’s risk mitigation strategy including the retention of £32.7m in contingency (26% of net scheme cost) 2.2 Approve proceeding to Stage 4 based on Stage 3 Design and Viability Assessment. 2.3 Approve £4.6m additional funding for consultant and direct fees and PCSA fees until the end of Stage 4, mainly to cover increased requirements under the Building Safety Act, noting total forecast fee spend to end of stage 4 is £14.55m. Page 126 2.4 Note the costed risk included in the cost model plus the addition of optimism bias to cover additional risk not fully mitigated within the costed risks. 2.5 Note that while the FLCR scheme is based on a low carbon, policy compliant design, the gas [1] powered EC1 Energy Centre will be removed from the FLC&R site, its future to be resolved as part of a separate strategy for a borough-wide heat network (including Bunhill) that will form a future paper to Executive, also noting the issues set out in section 3.8. 2.6 Note the intention to develop of a wellbeing offer for local residents to take advantage of the co [1] location of leisure and medical facilities. 2.7 Note the full General Fund deficit of £31.029m and Housing Revenue Account (HRA) deficit of £3.187m based on current total cost including all contingencies. 2.8 Approve re-allocation of £6.55m of General Fund capital programme borrowing to FLCR, as set out in para 3.7.20 to mitigate additional revenue pressures of up to £0.711m per annum. 2.9 Note the intention to engage with the GLA to assess any opportunities to secure additional grant to support the affordable housing within the scheme. 2.10 Note that additional Executive approval will be sought prior to award of a construction contract at RIBA Stage 5 DECISIONS AGREED RECOMMENDATIONS Reasons for the decision – as detailed in the report Other options considered – as detailed in the report Conflicts of interest / dispensations granted – none
Word for word from the decision Islington published for this meeting. Source: democracy.islington.gov.uk

Follow this further

Built from Islington's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
24.07.18 Finsbury Leisure Centre and Residential CGIsAppendix 1 4 MB Copy on its way
PDF
FLC Viability 5 DRAFT comparison: Jun 24 vs Aug 23Appendix 3 145 KB Copy on its way
PDF
24.03.28: FLCR: Risk Register Rev 21 (Current)Appendix 4 105 KB Copy on its way
PDF
240417 V3 FLC Full EQIAAppendix 7 177 KB Copy on its way
PDF
Finsbury Leisure Centre RedevelopmentReport 310 KB Copy on its way

More from Islington Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 Q1 Financial Risk Monitor 2026-27Recommendations: i. Noted the Q1 Financial Risk Monitor for 2026/27, including the key financial risks, forecast pres... Noted Open
17 Sep 2026 Consultation on the proposed New Tenancy ConditionsRecommendations: i. Noted the reasons why the Council is proposing to update its Tenancy Conditions ii. Agreed that t... Noted Open
17 Sep 2026 Response to Housing Scrutiny Review - New Build Homes May 2024Recommendations: i. Agreed the responses to the recommendations made by the Housing Scrutiny Committee, as set out in... Agreed Open
17 Sep 2026 Response to Overview and Scrutiny Committee Review - Financial ResilienceRecommendations: i. Agreed the Council’s response to the recommendations set out in the Review of Financial Resilienc... Agreed Open
17 Sep 2026 Response to the Overview and Scrutiny Committee - Progressive ProcurementRecommendations: i. Welcomed the findings of the Corporate Resources and Economic Scrutiny Committee (now Overview an... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies