London Borough of Islington
Executive, Thursday 22 January 2026 at 5.00pm

Procurement strategy and contract award for Finsbury Wellbeing Campus

Approved Executive 2 papers

AI summaryThe Executive approved the procurement strategy and awarded a contract to Alliance Leisure Limited as development partner for the Finsbury Wellbeing Campus, from concept design through to completion. Further approval will be needed before main construction.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedAs development partner for the campus project
MoneyNot stated
What happens nextDetailed design stageRIBA Stage 4, then further Executive approval
Who it affectsFinsbury Wellbeing CampusProject from concept design to completion

What was decided

Approved the procurement strategy and the proposed award of contract to Alliance Leisure Limited as development partner to deliver the Finsbury Wellbeing Campus project from concept design to completion, covering RIBA stages 2-7, subject to terms.

Delegated authority to the Corporate Director of Community Wealth Building, following consultation with the Executive Member for Health and Social Care, to award the contract and progress the scheme to detailed design, RIBA Stage 4.

Noted that further Executive approval will be sought before the project moves into the main construction phase, RIBA stages 5-7.

Why

As detailed in the report.

The Executive noted a risk mitigation strategy including programme governance arrangements and significant contingency and optimism bias provisions within the approved budget.

What happens next

The Corporate Director of Community Wealth Building will award the contract to Alliance Leisure Limited in consultation with the Executive Member for Health and Social Care.

The scheme will progress to detailed design, RIBA Stage 4.

The project will return to the Executive for further approval before main construction, RIBA stages 5-7.

Implications

  • Risk: A risk mitigation strategy is in place, including programme governance and significant contingency and optimism bias provisions within the approved budget.

Who and where

  • The Finsbury Wellbeing Campus project, covering RIBA stages 2-7 from concept design to completion.

Timeline

  • 2026-01-22: Executive agreed recommendations and awarded the development partner contract.
  • RIBA Stage 4: Scheme to progress to detailed design following contract award.
  • RIBA stages 5-7: Main construction phase, subject to further Executive approval.

Plain English for the jargon

  • RIBA stages 2-7: Royal Institute of British Architects work stages covering concept design through to construction completion.
  • RIBA Stage 4: Detailed design stage of the project.
  • RIBA stages 5-7: Main construction phase of the project, subject to further Executive approval.
  • Development partner: A contractor appointed to deliver the project from design through to completion, in this case Alliance Leisure Limited.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item446

Resolved

Recommendations: 1.1 To approve the procurement strategy set out in the report and proposed award of contract to Alliance Leisure Limited (ALL) as development partner to deliver the Finsbury Wellbeing Campus (FWC) project from concept design to completion (RIBA stages 2-7), subject to terms. 1.2 To delegate to the Corporate Director of Community Wealth Building, following consultation with the Executive Member for Health & Social Care, the authority to award a contract to ALL and to progress the scheme to detailed design stage (RIBA Stage 4), in line with the procurement strategy and other relevant governance. 1.3 To note that further Executive approval will be sought before the project moves into the main construction phase (RIBA stages 5-7). 1.4 To note the risk mitigation strategy including programme governance arrangements and significant contingency and optimism bias provisions within the approved budget. Decisions : AGREED 1. recommendations. 2. That thanks be extended to officers for their work on this project. Reasons for the decision – as detailed in the report Other options considered – as detailed in the report Conflicts of interest / dispensations granted – none
Word for word from the decision Islington published for this meeting. Source: democracy.islington.gov.uk

Follow this further

Built from Islington's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
251208 Summary proposal slidesAppendix 1 3 MB Copy on its way
PDF
Procurement strategy and contract award for Finsbury Wellbeing CampusReport 135 KB Copy on its way

At this meeting

Whole meeting

On this subject at Islington

Search all
  1. Procurement strategy and contract award for Finsbury Wellbeing CampusThis decision
  2. Procurement strategy for Short Breaks - I032734Approved
  3. Procurement strategy for insurance policies (casualty, property and terrorism) - 1033237Approved
  4. Procurement Strategy for Domestic Gas Boiler Installations, Servicing and Repairs - I032725Approved
  5. Procurement strategy for supported housing and floating support framework - 1031878Approved
  6. Procurement strategy for pan-London postal goods and services - 1032563Approved

More from Islington Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 Q1 Financial Risk Monitor 2026-27Recommendations: i. Noted the Q1 Financial Risk Monitor for 2026/27, including the key financial risks, forecast pres... Noted Open
17 Sep 2026 Consultation on the proposed New Tenancy ConditionsRecommendations: i. Noted the reasons why the Council is proposing to update its Tenancy Conditions ii. Agreed that t... Noted Open
17 Sep 2026 Response to Housing Scrutiny Review - New Build Homes May 2024Recommendations: i. Agreed the responses to the recommendations made by the Housing Scrutiny Committee, as set out in... Agreed Open
17 Sep 2026 Response to Overview and Scrutiny Committee Review - Financial ResilienceRecommendations: i. Agreed the Council’s response to the recommendations set out in the Review of Financial Resilienc... Agreed Open
17 Sep 2026 Response to the Overview and Scrutiny Committee - Progressive ProcurementRecommendations: i. Welcomed the findings of the Corporate Resources and Economic Scrutiny Committee (now Overview an... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies