Item10
Resolved
RESOLVED, for the reasons set out in paragraphs 3.1 - 3.2 and elsewhere within the report, that the recommendations at paragraph 2.1 - 2.2 adopted. The Leadership Team: 2.1 Approved the delivery of a £2.5 million capital project to purchase properties (to include all additional expenditure, fees, costs and stamp duty land tax payments, if any) to extend the Council’s in-house supported accommodation provision to accommodate an additional twelve care leavers in line with the specification and benefits set out in this paper. 2.2 Delegated authority to the Director of Social Investment and Property to approve the terms for the individual property purchases (subject to legal and financial due diligence) and enter into any associated legal documents to deliver the project. Action by: Executive Director of Housing and Social Investment
Word for word from the decision Kensington and Chelsea published for this meeting.
Source: www.rbkc.gov.uk