RESOLVED that:- (a) the actions taken or contemplated on the respective cases set out in paragraphs 6-123 of the report to be endorsed; (b) the establishment of working protocols with the Environment Agency be endorsed as outlined in paragraphs 129 and 130 of the report; (c) the Head of Planning Application Group be recommended to include an item on Kent County Council’s work in partnership with the Environment Agency at a future training event; and (d) the Head of Planning Applications Group be requested to correspond further with Her Majesty’s Courts Service on the delays occurring within the Kent Court system in dealing with breaches of planning control. (2) In accordance with Committee Procedure Rule 2.20(3), [name removed] dissension from the decision in relation to St Edmund’s School, Dover contained in paragraphs 112 to 115 of the report was recorded.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report by Head of Planning Applications Group to the Regulation Committee on 19th September 2006
Summary: Update for Members on planning enforcement matters.
Recommendation: To endorse the actions taken or contemplated on respective cases.
Local Member: n/a Unrestricted
Introduction
1. This report provides an update on enforcement and monitoring work carried out by the Planning Applications Group since the May 2006 Regulation Committee. The report is divided into 3 main sections – those cases
§ where formal enforcement action has been taken; § which are currently under-investigation; and § that have been resolved since the last meeting
The report also gives details of site monitoring and progress on the introduction of the chargeable site monitoring arrangements for minerals development.
2. Since the January meeting of the Regulation Committee, resources have been focussed on 9 sites where formal enforcement action has been taken, 22 cases where investigations are underway and a further 11 cases which have been satisfactorily resolved. In addition, monitoring visits on permitted sites have been undertaken on 7 sites.
3. Members will be aware that enforcement casework is considerably complex requiring sound legal solutions. Resources are targeted in accordance with the Council’s Enforcement Protocol to those sites where the activities being carried out have the potential to create the greatest environmental damage. These are investigated as a priority. Each case has to be considered on its own merits and in the context that enforcement action is a discretionary function. Action should only be taken as a last resort and only where it is expedient to do so. In delivering this part of the planning service, there is often an expectation to deliver results that fall outside the control of the planning authority, particularly with regard to timescales. Once formal action has been instigated the timescales and commitments involved are set by other parties i.e. the Planning Inspectorate or the Court Administrators. . Update on Enforcement Activities Cases Where Formal Action has been Taken
Deal Field Shaw, Charing 4. This former landfill site is also the subject of an exempt report to these papers (Item 14).
Larkey Wood, Chartham 5. This site within a Special Landscape Area is the subject of an exempt report to these papers (Item 12).
7.1Item 7 Update on Planning Enforcement Issues
Detling Quarry, Detling 6. This is an active chalk quarry, which lies within an Area of Outstanding Natural Beauty. There have been a number of operational irregularities over the past 3-4 years, absorbing a great deal of officers’ time. Allied to this has been non-quarry related breaches connected with the site occupier. Court action failed to secure the removal of articles, debris, buildings and vehicles remaining on site in breach of a confirmed Enforcement Notice. The need for any further litigation under existing authorisation from Members has been under regular review with the County Solicitor.
7. Meanwhile, the site occupier appealed the refusal of planning permission by Maidstone Borough Council for an independent residential and business use within the quarry. The appeal was heard on 23 and 24th May 2006. Maidstone Borough Council was the lead authority but my Group assisted the Inquiry by presenting background evidence including the full planning history of the quarry.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.