Resolved
RESOLVED that the report be noted and that the proposed changes to the format of future progress reports be approved.
Governance and Audit Committee noted this item on Wednesday 5 March 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted and that the proposed changes to the format of future progress reports be approved.
Item No: 4 By: The Head of Audit & Risk
To: Governance and Audit Committee - 5 March 2008
Subject: INTERNAL AUDIT PROGRESS REPORT
Accountable Officer: The Head of Audit & Risk
Classification: Unrestricted
Summary: This report summarises the outcomes of Internal Audit activity and proposes some changes to the format of future progress reports.
FOR INFORMATION AND DECISION
INTRODUCTION
1. The format of this report, which was agreed at a previous meeting, is as follows:
Annex B Audits completed to date. Audits appearing for the first time are shown in bold. Nine were completed in this period, which are listed in the table below:
Directorate Audit Title Assurance CED Unix Operating System Substantial CED Legal services Electronic Document Security Substantial CED A pre implementation review of the OneOffice Not Applicable Commercial system (replaces SWAPS & Trading System) services to ensure that ICT security is built into the system. CF&E Eligibility for Foster & Adoption Allowances Substantial KASS Westview Integrated Care Service High E&R A Major Road Scheme – East Kent Access Substantial Phase 1 E&R KHS Network Management Confirm Works Not Applicable Orders & Summit Cost Capture System CMY CRB disclosure checks for volunteers Minimal CMY Fastlane Limited
Annex C Summary information, with the directorates’ response for audits where control is assessed as minimal.
Annex D Brief details of audit work completed in the period.
4: 1 Annex E Summary of directorates’ progress with the implementation of internal audit recommendations.
Members can see from Annex E that of the 76 recommendations due to be in place, 57 have been actioned and 19 remain outstanding.
2. Members should note that the audit assurance expressed is at the time of issue of the audit report but before full implementation of the agreed management action plan. Directorates’ progress with the implementation of recommendations is followed up and reported at Annex D, after the date by which it has been agreed that action will be undertaken. Where a ‘minimal’ assurance has been given, there will be further re-evaluation in a six-monthly review.
3. Furthermore, each audit does not carry equal weight when forming the overall assurance on the operation of control within the Authority. Whilst the key systems will have a major impact, other systems, for example establishment audits, become more significant when the outcomes of a number of similar audits have been obtained. In this instance, the key indicator is the trend in audit assurances within a directorate and across the Authority.
IRREGULARITIES
4. Since the end of November four cases of suspected irregularity have been reported, each involving either KCC finances or business processes. Details of completed irregularity investigations are given in my separate report at agenda item 9
PERFORMANCE OF INTERNAL AUDIT
5. Internal Audits performance against a range of agreed indicators, where information is available, is shown below:
Performance Indicator Target Actual (Apr – Jan) Productivity and Efficiency • % of available time spent on direct audit work 80% 79% • % of draft reports completed within 10 days of 89% 96% finishing fieldwork • Preparation of annual plan By March Reported 7.3.07 • Periodic reports on progress G&A Cttee Reported: meetings 07.03.07 29.06.07 19 09.07 04.12.07 • Preparation of annual report Prior to annual Reported 29.06.07 assurance statement Quality of Service • Average Client satisfaction score 70% 93% Staff Management • Staff with professional qualifications (including 60% 71% trainees) 4: 2 PROPOSED CHANGES TO INTERNAL AUDIT PROGRESS REPORT
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 14 pages | DownloadRead as text |
Follow Governance and Audit Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Oct 2026 | Minutes of the meeting held on 23 July 2026RESOLVED that the minutes be signed by the Chair as a correct record of the meeting held on 23 July 2026. | Decided | Open |
| 15 Oct 2026 | Draft Statement of AccountsRESOLVED that the Committee: a. NOTE the Kent County Council Auditor’s Interim Annual Report 2025–26; b. NOTE the Aud... | Noted | Open |
| 15 Oct 2026 | Letters of Representation - Kent County Council and Kent Pension FundRESOLVED that the Committee approve the Letters of Representation for Kent County Council and the Kent Pension Fund, ... | Approved | Open |
| 23 Jul 2026 | Minutes of the meeting held on 19 May 2026RESOLVED that the minutes of the meeting held on the 19 May 2026 were a true and accurate record and a paper copy sho... | Decided | Open |
| 23 Jul 2026 | Verbal Update on Committee BusinessIt was agreed that a draft version of the tracker format would be shared with Members at the next meeting to provide ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.