Resolved
RESOLVED to endorse the actions taken or contemplated on the respective cases set out in paragraphs 9 to 21 of the report and those contained in the Schedules set out in Appendices 1 to 3.
Regulation Committee decided this item on Thursday 10 September 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to endorse the actions taken or contemplated on the respective cases set out in paragraphs 9 to 21 of the report and those contained in the Schedules set out in Appendices 1 to 3.
Update on Planning Enforcement Issues
Report by Head of Planning Applications Group to the Regulation Committee on 10th September 2009
Summary: Update for Members on planning enforcement matters.
Recommendation: To endorse the actions taken or contemplated on respective cases.
Local Member: Given by case in Appendices 1 to 3 Unrestricted
Introduction
1. This report provides an update on enforcement and monitoring work carried out by the Planning Applications Group since the 19th May 2009 Regulation Committee.
2. Summary schedules of all current cases have been produced (see Appendices 1 to 3). The cases are organised by District and the local County Member(s) identified in each case. Members are already notified on any new County enforcement cases under the existing Enforcement Protocol arrangements. The summary tables cover unauthorised breaches of planning control and those occurring on permitted sites, whether minerals or waste related or those further connected with County Council developments.
3. The schedules are designed to help focus officer and committee time on those cases requiring the most attention. The accent is on live and active cases along with those resolved between Meetings (see paragraph 15). They exclude cases where other agencies are pursuing a solution. This close targeting of effort is in accordance with the County Council’s Enforcement Protocol. A phased approach is taken, with an initial attempt to negotiate an informal settlement. Formal and more costly action is used as a last resort to stop determined contraveners in accordance with Government guidance and enforcement good practice. The priority is always to urgently stop any serious environmental damage or unacceptable level of amenity impacts. Restoration tends to take place over a longer timescale.
Report Format
4. Cases have been taken from the appended schedules and expanded reports produced. These in turn are presented under the following categories:
• Achievements / successes [including measurable progress on existing sites] • New cases, especially those requiring Member endorsement for action • Significant on-going cases • Other cases of interest and those requested by Members
5. Members may wish to have verbal updates at Committee on particular sites from the schedules, (ideally with prior notice) or reports returned to the next Meeting. The report continues to give details of site monitoring and progress on chargeable site monitoring arrangements for minerals development. Update on Planning Enforcement Issues
Meeting Enforcement Objectives
6. Planning enforcement is a high profile County Council function. The powers used derive from planning statutes but the type and degree of action taken is discretionary. That is to allow a flexible and proportionate approach to cases. The resources allocated have to be balanced against those directed to other planning services, in turn referenced to national and corporate BVPI targets. There also needs to be a balance between responding at speed to live cases within our Enforcement Protocol commitments and attending to longer-term restoration objectives on existing sites.
7. Efforts have been concentrated chiefly on defending formal actions that have previously been taken and have progressed or are likely to progress to planning inquiry or the High Court. Resources have been focussed on 4 sites where formal enforcement action has been taken, 4 cases where investigations are underway and a further 12 cases have been satisfactorily progressed or resolved. Amongst monitoring visits on permitted sites there have been 18 chargeable visits.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Planning Enforcement IssuesReport | 19 pages | DownloadRead as text |
Follow Regulation Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Oct 2025 | Election of ChairRESOLVED that [name removed] be elected Chair of Regulation Committee. | Decided | Open |
| 16 Oct 2025 | Election of Vice-ChairRESOLVED that [name removed] be elected as Vice-Chair of Regulation Committee. | Decided | Open |
| 16 Oct 2025 | Update from the Public Rights of Way and Access ServiceRESOLVED that the report be noted. | Noted | Open |
| 16 Oct 2025 | Update on Planning Enforcement CasesRESOLVED to note the report and endorse the enforcement strategies outlined in Appendices 1 and 2. | Noted | Open |
| 21 Jan 2025 | MembershipRESOLVED to note that [name removed] had joined the committee. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.