RESOLVED that:- (a) the content of paragraph 7 of the report concerning the surface engineering of the site and related technical works be endorsed on the proviso that details are first lodged with the Head of Planning Applications group for enforcement and verification purposes; and (b) the report form the basis of any briefing concerning the site given to local residents or other adjoining land interests. EXEMPT ITEMS (Open Access to Minutes) (Members resolved under Section 100A of the Local Government Act 1972 that the public be excluded from the meeting for the following business on the grounds that it involved the likely disclosure of exempt information as defined in paragraphs 5 and 6 of Part 1 of Schedule 12A of the Act.)
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
1. I referred to this report, under Appendix 1, Schedule 1, No.1, within Item 7 of these papers.
2. Members are aware of the long planning enforcement history in this case and the eventual need for the County Council to acquire this landfill site in order to bring the situation to an end. The Authority has control of its restoration and management. Given the interests of local residents and the public investment involved in direct action here, I am keeping Members informed as to progress.
Site restoration
3. KCC Waste Management is project managing this land recovery project. I have sought an update from them on the current situation at the site. I have been briefed as follows:
“As you are probably aware we have done a significant amount of work here looking at both the problem and determining the solution.
In essence the next stages involve putting in a "holding tank" so that we can pump leachate to it from the sump. From there it is easily tankered away. Initially the tank will be surface mounted, but once we have a system in place and working effectively, then sunk into the ground and made "unobtrusive". At the same time the drains which run around the periphery of the site will be reinstated and designed to absorb rain water "run off".
We then need to tackle the root cause of the problem. The "capping liner" required under the planning approval was never placed so rain water enters the site where it remains trapped because the site liner continues to do its job effectively! The site fills up with leachate which we then need to dispose of which is an expensive and frankly unsustainable operation.
Whilst it is understood the finished contours could perhaps have been better engineered what we now propose to achieve is a basic tidying up of the boundary; treatment so that Update on Planning Enforcement Issues at Deal Field Shaw (Shaw Grange), Charing
the existing difference in contour heights is smoothed out together with the placing of a geotechnical liner to prevent the ingress of water. This measure alone will significantly improve the environmental performance of the site and will hopefully ensure we are able to satisfy our general obligations under Part 2A of the Environmental Protection Act (EPA) 1990.
It is not proposed to remove material off site since this is likely to be both a very expensive operation and in "best" engineering terms, unlikely to be of any significant benefit. Also exposing significant quantities of previously tipped material (including the putrescible element we are aware of) is likely to have a detrimental impact on nearby residential properties, not least because of the unpleasant odours likely to be released.
What is proposed is that a liner and cover material is placed over the entire tipped area to seal the site, and in turn reduce the volumes of produced leachate. It is proposed to keep this to the absolute minimum to guarantee success which is likely to increase the overall height of between 300mm to 500mm. I am sure you will agree this is acceptable given the very positive environmental improvements we will achieve.
I am currently undertaking an ecological survey of the site which I am hoping will confirm our view that there are no species present which we will need to translocate. Otherwise there might be a delay getting on within the current financial year.
Not doing anything is not an option here. Levels of leachate within the site continue to rise and need to be carefully monitored and managed. This is a costly operation and does not address the problem.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.