Resolved
RESOLVED that the projected outturn for the Chief Executive’s Department and Financing Items for 2010/11 based on the third quarter’s monitoring report to Cabinet be noted.
Corporate Policy Overview and Scrutiny Committee noted this item on Thursday 31 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the projected outturn for the Chief Executive’s Department and Financing Items for 2010/11 based on the third quarter’s monitoring report to Cabinet be noted.
Members of the POSC are asked to note the third quarter’s budget monitoring report for 2010/11 due to be reported to Cabinet on 4th April
FOR INFORMATION
1. Introduction
1.1This is a regular report to this Committee on the forecast outturn for Chief Executives Department and Financing Items budgets within the Corporate Services portfolios.
2. Forecast Outturn
2.1A detailed quarterly budget monitoring report is presented to Cabinet, usually in September, December and March, and a draft final outturn report in June. These reports outline the full financial position for each portfolio and are reported to POSCs after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report.
2.2The third quarter’s monitoring report for 2010/11 will be presented to Cabinet on 4th April 2011. Extracts from the annex for the Chief Executives Department for the portfolios reporting to this POSC and the annex for Financing Items are attached as appendix 1.
2.3Revenue Budget
Chief Executives Department
2.3.1 Since the last report to this POSC in January the forecast net under spend for CED has increased from £197k to £1.101m. Some of this is due to the moratorium agreed by CMT for the remainder of this financial year to help deliver next year’s budget. 2.3.2 The additional significant variations other than moratorium since the last report are :
a. Under spend of £83k within Democratic Services on members IT support. We have reviewed the level of the member IT budget for 2011/12. b. Personnel & Development are forecasting a net under spend of £276k. This derives from additional income from trading activities with schools and other local authorities, and under spends on a number of other budget headings. The only under spend of note is £70k re-phasing of work streams to deliver the changes to Total Contribution Pay which will be subject to request for committed roll-forward and therefore not available to help deliver 2011/12 budget. c. £198k rates rebate on Invicta House and Sessions House. These rebates were confirmed too late to include as specific items in 2011/12 budget but will contribute to the target for savings from property holding costs from Total Place. Property are also predicting an under spend on staffing budgets of £120k as a result of covering the Director of Property post internally and holding other posts vacant d. Additional forecast income earned by Legal Services and reduced related costs, have resulted in an increased forecast surplus of £137k to £0.453m.
Financing Items
2.3.4 The forecast under spend on Financing Items has increased from £5.241m reported to this POSC on 13th January (exception report to Cabinet 10th January) to £6.750m in the third quarter’s report. Most of this variation (£1.106m) was reported to Cabinet in the exception report on 2nd February and related to further variation on debt charges and contribution to restructure reserve.
2.4Capital
2.4.1 The monitoring shows a re-phasing of £3.366m from 2010/11 to 2011/12 and 2012/13. This includes £1.282m on the Gateway Programme as outlined in paragraph 1.2.4.1 of the attached appendix and £1.123m on Sustaining Kent (Maintaining the Infrastructure) as outlined in paragraph 1.2.4.2 in attached appendix.
3.1Members of the POSC are asked to note the projected outturn for the Chief Executive’s Department and Financing Items for 2010/11 based on the third quarter’s monitoring report to Cabinet.
Background Documents: 1) Cabinet 4th April 2011 – Revenue and Capital Budgets, Key Activity and Risk Monitoring
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring Report : Corporate Services 2010/11Report | 22 pages | DownloadRead as text |
Follow Corporate Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jan 2012 | Minutes of the meeting on 3 November 2011RESOLVED that the minutes of the meeting held on 3 November 2011 are correctly recorded and that they be signed by th... | Decided | Open |
| 11 Jan 2012 | Financial Monitoring 2011/12RESOLVED t hat the projected outturn for the Business Strategy and Support Directorate, the Financing Items for 2011/... | Noted | Open |
| 11 Jan 2012 | KCC Quarterly Performance Report, Quarter 2, 2011/12 including mid year Business Plan monitoringRESOLVED that the report and comments made by Members be noted. | Noted | Open |
| 11 Jan 2012 | Budget 2012/13 and Medium Term Financial Plan 2012/15RESOLVED that the comments by Members and the revenue and capital budget proposals for the Corporate Services portfol... | Noted | Open |
| 11 Jan 2012 | Procurement PracticeIt was agreed that the outcome of the meeting on 11 January 2012 between [name removed], [name removed] and [name rem... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.