RESOLVED that t he progress on the centralisation and restructure of the Finance function be noted.
Corporate Policy Overview and Scrutiny Committee noted this item on Wednesday 6 July 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that t he progress on the centralisation and restructure of the Finance function be noted.
As part of ‘Change to Keep Succeeding’, the Finance function was centralised on 4 April. In reality, little changed in those first few weeks, but we have been working on options for delivering a Finance function fit for the future, for around 30% less cost.
Back in December 2010, on the back of the County Council decision to approve the new organisational structure, we asked for a working group of just three finance staff to produce a paper for the then Finance Strategy Board (FSB) to consider in early February 2011. The group produced an excellent options appraisal paper which they presented to the FSB on 11 February. The options were debated and resulted in a draft outline proposal being presented to the Corporate Management Team (CMT) on 1 March.
CMT endorsed the direction of travel set-out in the report. Consequently, an eMail was sent to all Finance staff on 2 March, advising them of the outline proposal. Since then, regular update eMails have been sent to all Finance staff keeping them informed of progress.
3 THE DRAFT PROPOSAL
The Finance function currently has 572.5 full-time equivalent posts. Of these, approximately 199.41 are directly funded by either the Pension Fund, the
1 Ftes estimated pro rata to budget Insurance Fund, external grant (such as dedicated Schools Grant) or external funding (such as schools).
The objectives of the restructure are: - to reduce net cost by around 30% (subject to a formal decision being taken to that effect as part of the budget process) - to use the remaining resource to best effect, which will require: o a thorough review of all tasks undertaken within the function to determine what we can ‘stop doing’ o adopting a risk based approach to supporting budget managers o developing our systems to reduce budget managers’ reliance upon Finance staff and to avoid the need for manual intervention - to comply with the organisation design principles of no more than five tiers of management and a span of control for any manager of between six and eight, where possible.
The table below sets-out the financial and fte target we are aiming for:
FTEs £000 Total budgeted provision 572.5 19,269,456 Less income & DSG* 199.4 6,711,084 Net for 30% target* 373.1 12,558,372 30% savings target * 111.9 3,767,512 Current vacancies 29.3 766,446 Total target budget after 30% reduction 460.6 15,501,944
The attached structure provides initial proposals as to how this may be achieved. However more detailed work needs to be done in the next few months to determine task’s and responsibilities of each team and to firm up numbers and grades of FTEs needed. The figures shown on the attached are planning targets rather than set in stone. All costs shown are also based on indicative salary plus on-costs. All posts will be subject to evaluation.
4 PROGRESS TO DATE
a) Structure In order to get this more detailed work underway, appointments have already been made on a six month secondment basis, to seven of the posts in the structure. These are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Centralisation and restructure of the Finance functionReport | 4 pages | DownloadRead as text |
PDF |
Item B3: Structure Chart A4Report | 1 pages | Download |
Follow Corporate Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jan 2012 | Minutes of the meeting on 3 November 2011RESOLVED that the minutes of the meeting held on 3 November 2011 are correctly recorded and that they be signed by th... | Decided | Open |
| 11 Jan 2012 | Financial Monitoring 2011/12RESOLVED t hat the projected outturn for the Business Strategy and Support Directorate, the Financing Items for 2011/... | Noted | Open |
| 11 Jan 2012 | KCC Quarterly Performance Report, Quarter 2, 2011/12 including mid year Business Plan monitoringRESOLVED that the report and comments made by Members be noted. | Noted | Open |
| 11 Jan 2012 | Budget 2012/13 and Medium Term Financial Plan 2012/15RESOLVED that the comments by Members and the revenue and capital budget proposals for the Corporate Services portfol... | Noted | Open |
| 11 Jan 2012 | Procurement PracticeIt was agreed that the outcome of the meeting on 11 January 2012 between [name removed], [name removed] and [name rem... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.