Education and Young People's Services Cabinet Committee agreed this item on Wednesday 8 July 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Education and Young People’s Services Cabinet Committee endorsed the decision to be taken by the Cabinet Member for Education and Health Reform to: a) allocate £1,384,353.56 from the Education and Young People’s Services Capital Budget, being Kent County Council’s contribution towards the priority school building scheme which has been agreed with the Education Funding Agency (EFA), subject to any necessary additional works or necessary variations. b) The Corporate Director for Education and Young People’s Services in consultation with the Cabinet for Education and Health Reform be authorised to negotiate with the EFA as to the necessity and cost of any additional work or variations identified, to ensure that any further contribution is minimised. Any agreements will not exceed current approved financial limits; and c) The Executive Scheme of Delegation for Officers set out in Appendix 2 Part 4 of the Constitution (and the directorate schemes of sub-delegation made thereunder) provides the governance pathway for the implementation of this decision by officers. In this instance the Director of Property and Infrastructure Support is expected to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Education and Young People's Services Cabinet Committee, 7 pages
Recommendation
The Education and Young People’s Services Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Education and Health Reform on the decision to:
i. Allocate £1,384,353.56 from the Education and Young People’s Services Capital Budget, being Kent County Council’s contribution towards the priority school building scheme which has been agreed with the Education Funding Agency (EFA), subject to any necessary additional works or necessary variations. ii. The Corporate Director for Education and Young People’s Services in consultation with the Cabinet for Education and Health Reform be authorised to negotiate with the EFA as to the necessity and cost of any additional work or variations identified, to ensure that any further contribution is minimised. Any agreements will not exceed current approved financial limits iii. The Executive Scheme of Delegation for Officers set out in Appendix 2 Part 4 of the Constitution (and the directorate schemes of sub- delegation made thereunder) provides the governance pathway for the implementation of this decision by officers. In this instance the Director of Property and Infrastructure Support is expected to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts.
1. Introduction
1.1The Swale district section of the Kent Commissioning Plan for Education Provision 2013-18 identified a significant pressure in Reception year places. The Commissioning Plan identified a need to provide additional places on the Isle of Sheppey from September 2014 and Halfway Houses Primary School agreed a temporary 1FE expansion for September 2014 and admitted 90 children into Reception Year (30 additional children).
1.2Halfway Houses Primary School was successful in its application to be rebuilt under the Government’s priority school building scheme. The project is to be delivered by the EFA. Halfway Houses new school building will be rebuilt on the site of the former Danley Middle School. The EFA will be commencing the procurement process shortly and, subject to successful design and planning approvals, it is hoped that the project will be completed during 2016.
1.3KCC wished to use the opportunity of the school being rebuilt to incorporate additional works via the Contract that were over and above the EFA’s funding allocation, in order to provide an additional 70 places to take the school capacity from 560 Primary places to 630 Primary places (3FE). KCC has agreed the cost assessment provided by the EFA at the feasibility stage for the Additional Works and will contribute £1,384,353.56 plus VAT. KCC recognises this is an estimate and that the total cost of the Additional Works may be higher or lower than this.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Education and Young People's Services Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.