Education and Young People's Services Cabinet Committee noted this item on Wednesday 8 July 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED that:- (a) the responses to questions by Members be noted; and (b) t he Education and Young People’s Services Cabinet Committee endorsed the decision to be taken by the Cabinet Member for Education and Health Reform to approve the following capital projects, and allocate funding, from the Education and Young People’s Services Capital Budget, of the following amounts in order that the proposals may go ahead: (i) a. A further £2.3m for Tunstall CE Primary School, Swale. b. A further £2.2m for Kings Hill Academy, Tonbridge & Malling. c. £9m to the rebuild and expansion of Portal House School, Dover. d. £1.4m to the expansion of Green Park Primary School, Dover. e. £6m to the building of Finberry School, Ashford. f. £2.5m to the expansion of The Judd School, Tonbridge & Malling. (ii) To expand Portal House School by 20 places from 1 September ... view the full minutes text for item 80.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Education and Young People's Services Cabinet Committee, 13 pages
Recommendations
The Education and Young People’s Services Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Education and Health Reform on the decision to approve the following capital projects, and allocate funding, from the Education and Young People’s Services Capital Budget, of the following amounts in order that the proposals may progress:
(i) a. A further £2.3m for Tunstall CE Primary School, Swale. b. A further £2.2m for Kings Hill Academy, Tonbridge & Malling. c. £9m to the rebuild and expansion of Portal House School, Dover. d. £1.4m to the expansion of Green Park Primary School, Dover. e. £6m to the building of Finberry School, Ashford. f. £2.5m to the expansion of The Judd School, Tonbridge & Malling.
(ii) To expand Portal House School by 20 places from 1 September 2015 as part of the project to rebuild the school on its current site.
(iii) The Executive Scheme of Delegation for Officers set out in Appendix 2 Part 4 of the Constitution (and the directorate schemes of sub-delegation made thereunder) provides the governance pathway for the implementation of this decision by officers. In this instance, the Director of Property and Infrastructure Support to be the nominated Authority Representative with the relevant agreements and to enter into variation as envisaged under the contracts. 1. Introduction
1.1The Kent Commissioning Plan for Education Provision 2015 – 19 identifies the need for additional school places. This report seeks the necessary approval for a number of projects which add school places. These fall into three categories:
a) Projects which have previously been agreed but costs have exceeded the estimated costs by more than the 10% officers have been given authority to deal with under delegated authority; b) Projects where KCC has undertaken statutory proposals which require a formal decision; and c) Expansion and new school proposals which now require KCC to agree to release the capital required to support the proposals.
1.2This paper sets out the detail to enable a decision to be taken in respect of each project.
2. Category A Projects
2.1Costs within the construction sector have risen significantly since the original estimates were made, with construction costs within late 2014 reaching unanticipated levels. Inflationary pressures continue and KCC is addressing these through endeavouring to secure contracts on a shared risk basis. 2015 inflationary pressures are continuing the upward trend, driven by skills shortages in the construction sector and raw material price demands.
2.2Project Cabinet Member Approved Revised Project Specific Decision Date Budget Budget Reasons Tunstall CEPS 15 May 2014 £4.82m £7.1m Design development, site investigations, highways works and abnormal costs Kings Hill 5 September 2014 £4.6m £6.8m Contamination Academy removal (asbestos), ground conditions and temporary accommodation
3. Category B Projects
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Education and Young People's Services Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.