Highways and Transportation schemes funded through Local Growth Fund Round Two
AgreedExecutive2 papers
Growth, Environment & Transport Cabinet Committee agreed this item on Tuesday 21 July 2015. Below is the council's own wording, with the papers it was decided on.
It was RESOLVED that the proposed decision to authorise the Council entering into agreement for the transfer of LGF to Network Rail in respect of the Ashford Spurs scheme and to Dover Harbour Board in respect of Dover A20 Improvements Scheme be endorsed.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 5 pages
From: Matthew Balfour, Cabinet Member for Environment and Transport
Barbara Cooper, Corporate Director for Growth, Environment and Transport
Stephanie Holt, Interim Director for Environment, Planning and Enforcement
To: Environment and Transport Cabinet Committee – 21 July 2015
Decision No: 15/00064
Subject: Highways and Transportation schemes funded through Local Growth Fund Round Two
Key decision: Affects 2 or more electoral divisions
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: For Cabinet Member Decision
Electoral Division: Ashford South and Dover Town
Summary: In January 2015 the Government announced a Growth Deal Extension, increasing Kent County Council’s Local Growth Fund allocation for Highways and Transportation projects to £109 million. Of the 24 transport projects allocated Local Growth Fund, four will be delivered by third party organisations. This includes the delivery of Ashford Spurs Rail Project by Network Rail and A20 Improvements in Dover as part of Dover Western Docks Revival to be managed by Dover Harbour Board.
Approval is sought to develop agreements for the transfer of funding and conditions of spend to Network Rail in respect of the Ashford Spurs scheme and Dover Harbour Board in respect of Dover A20 Improvements Scheme. This will enable the delivery of these two projects by the respective delivery organisation in accordance with Kent County Council requirements and the LEP Assurance Framework.
Recommendation(s):
The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Environment and Transport on the proposed decision, as follows and as indicated on the proposed decision sheet attached in Appendix 1 to:
Authorise the Council entering into agreement for the transfer of Local Growth Fund to the respective delivery organisation for; a) the Ashford Spurs Rail Project and;
b) the Dover A20 Improvement Scheme (as part of Dover Western Docks Revival)
1. Introduction
1.1In the Growth Deal announced in July 2014, the Government allocated £442 million from the Local Growth Fund to capital projects across the South East Local Enterprise Partnership (SELEP) area.
1.2In January 2015 a Growth Deal Extension was announced by Government, following SELEP Local Growth Fund Round Two submission.
1.3In total, through Rounds One and Two, £109m Local Growth Fund has been allocated towards the delivery of 24 Highways and Transportation projects in Kent.
1.4The Growth Deal extension included the allocation of funding for Ashford Spurs Rail Project and Dover A20 Improvements scheme.
1.5Through the Service Level Agreement with Essex County Council as the Accountable Body for SELEP, Kent County Council is responsible for the programme management of all Local Growth Fund projects in Kent. There are, however, specific projects for which third party organisations are responsible for delivering.
1.6The project management and delivery of the Ashford Spurs scheme will be undertaken by Network Rail, and the Dover A20 Improvements Scheme by Dover Harbour Board.
1.7Given that KCC is ultimately accountable to the LEP Accountability Board for Local Growth Fund spend within Kent, we are seeking formal agreements to be signed by the third party delivery agent to ensure that the Local Growth Fund conditions of spend and project delivery are transferred to each delivery organisation.
1.8The report provides i) an overview of Ashford Spurs and Dover A20 Improvements and ii) seeks support for entering into formal agreements with the third parties delivering each of these schemes to ensure they are progressed according to the requirements of the LEP Assurance Framework.
2. Ashford Spurs
2.1The Ashford Spurs scheme is a £4.52m project initiated by Kent County Council. Through the Growth Deal Extension, £2 million Local Growth Fund has been provisionally allocated to the project, subject to approval of the project by the SELEP Accountability Board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.