Resolved
RESOLVED that:- (a) the comments and responses to questions by Members be noted; and (b) the setting up of a Member Task and Finish Group to inform and identify the priority outcomes for the future of the service be agreed.
Growth, Environment & Transport Cabinet Committee noted this item on Friday 4 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that:- (a) the comments and responses to questions by Members be noted; and (b) the setting up of a Member Task and Finish Group to inform and identify the priority outcomes for the future of the service be agreed.
From: Matthew Balfour, Cabinet Member – Environment & Transport
Roger Wilkin, Interim Director Highways, Transportation and Waste
To: Environment & Transport Cabinet Committee – 4 December 2015
Subject: Kent County Council Highways, Transportation & Waste Soft Landscape Works - Service Review 2018/19
Non-Key decision
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: Environment & Transport Cabinet Committee March 2016.
Electoral Division: County Wide
Summary: One of the objectives included in the KCC Business Plan is to review the soft landscape works service from 2018/19, after current contracts expire. A number of options for the future service have been identified and require development. This report seeks cabinet approval to engage an Member Task and Finish Group to review and identify the priority outcomes for the service. The recommendations from the Group will be reported back to Envrionment &Transport Cabinet Committee for final decision in March 2016.
Recommendation: The Cabinet Committee is asked to set up an Member Task and Finish Group to inform and identify the priority outcomes for the future of the service.
1. Introduction
1.1Highway Operations Soft Landscaping Team are responsible for the management of trees and vegetation within the highway boundary in urban and rural areas (8,500km of road network). The service is delivered through a balance of arrangements with districts and parishes and through publicly procured contracts with SME contractors. An earlier review of the service determined that co-termination of works contracts in 2017/18 would provide an opportunity to review the future service delivery of the works element.
1.2The lead-in time to replace existing works arrangements, including procurement requirements, negotiations and mobilisation periods means that an executive decision on the preferred option is required by the end of March 2016. A timeline is attached as Appendix 2.
2. Background, Options and Objectives
2.1A list of the soft landscape procured contracts is attached at Appendix 1. The current annual cost of soft landscape works is £2.6m. Notably reductions of £1.1m (30%) were made in 2011/12. The MTFP targeted savings of £385k (15%) are proposed for 2018/19. The MTFP savings will result in reduced service levels.
2.2In 2015/16 the majority of the soft landscape spend is on scheduled works for urban and rural grass cutting, shrub and hedge maintenance, tree works and weed control. Regular procurement has resulted in lowering prices. These prices are used to benchmark the current arrangements with districts and parishes. Due to the frequent testing of the market officers are confident the current prices reflect value for money.
2.3Five districts (and several parishes) currently provide the service on our behalf. These districts are reimbursed at the benchmarked rates and provide enhanced services at their own cost to meet their local needs. However the districts have expressed concerns that any further reduction in either funding or service levels will force them to hand back the service.
2.4Current works frequencies fall short of what the highways soft landscape asset requires for long term sustainability. Further reductions in the service will contribute to long-term degradation of the asset.
2.5In line with the planned review of the service and the new commissioning procedures a draft Diagnostic Report has been prepared. The draft Diagnostic Report outlines five possible options for the future of the service:
Option 1: Status Quo – continue with existing works frequencies and deliver the service through a mix of publicly procured contracts and through agreements with districts and parishes. A small amount of savings could be achieved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Kent County Council Highways, Transportation & Waste Soft Landscape Works: Service Review 2018/19Report | 7 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.