Resolved
It was RESOLVED that the report be NOTED.
Cabinet noted this item on Monday 27 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED that the report be NOTED.
Cabinet Members are asked to note this report, and to make comments to the Cabinet Member for Environment and Transport concerning the progress of the Pothole Blitz.
1. Introduction
1.1In April 2016, the Department for Transport announced that KCC is to be awarded £1.47m from a Pothole Action Fund for the the financial year 2016-17, with a view to enabling the permanent repair or prevention of up to 28,000 potholes.
1.2Whereas in previous years, such pothole campaigns have been delivered through the Highways Term Maintenance Contract (TMC), in the spririt of strategic commissioning, the Director of Highways Transportation & Waste approached Commercial Services Kent Limitied (CSKL) with a view to assessing the potential for providing a more locally responsive service through local suppliers, and managed through CSKL’s Teckal compliant arm.
1.3Consequently, a tender process was initiated, and this process resulted in the engagement of six local companies, each to deliver a Pothole Blitz in two districts each. The process resulted in very competitive prices, which are anticipated to be cheaper overall (inclusive of the CSKL overhead) than using the TMC.
1.4KCC’s Highways will retain overall control of the scheme, and will manage and fund activity through the relevant District Managers. CSKL will be accountable for day to day management of the local supply chain, and will be accountable for ensuring the quality of outcomes.
1.5Companies within the supply chain will be empowered to make “common sense” decisions about how each pothole repair is delivered, for example being able to determine whether additional works adjacent to the repair ordered should also be undertaken in the interest of good customer outcomes.
2.1Costs associated with the Pothole Blitz will be funded through the government’s Pothole Action Fund with additional funding being provided by KCC to a total of £3million to be spent on the programme.
2.2The local supply chain has been compliantly procured by CSKL, and their rates together with the CSKL overhead are comparable to those that would be payable were the Pothole Blitz being provided through the Term Maintenance Contract.
2.3Each Highway District manager will be assigned funding, initially on the basis of carriageway length, although this can be amended as the project progresses should particular districts demonstrably require a greater proportion of resource.
3. Project delivery
3.1The Pothole Blitz commenced on 14 June 2016, and is anticipated to continue through to October 2016.
3.2Each of the six local providers will operate in two districts, and will dedicate two pothole gangs per district to ensure that work is very locally responsive.
3.3Works will be identified and ordered by KCC Highways on the basis of the local knowledge of our local Highway Stewards, as well as information from our customers. Orders will be placed throught CSKL, who will manage the supply chain, and ensure that work is carried out to a suitable standard and on time.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Pothole BlitzReport | 3 pages | DownloadRead as text |
Follow Cabinet at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2026 | Minutes of the Meeting held on 22 July 2026RESOLVED that the minutes of the meeting held on 22 July 2026 were approved as a correct record. | Approved | Open |
| 1 Oct 2026 | 26/00055 - Revenue and Capital Budget Monitoring Report - Q1 2026-27It was RESOLVED that Cabinet agreed to: a) NOTE the revenue and ... view the full minutes text for item 153. | Agreed | Open |
| 1 Oct 2026 | Quarterly Performance Report, Q1 2026-2027It was RESOLVED that Cabinet agreed to note the Quarter 1 Performance Report and the actions being taken to address a... | Agreed | Open |
| 22 Jul 2026 | Minutes of the Meeting held on 25 June 2026RESOLVED that the minutes of the meeting on 25 th June 2026 were a correct record and that they be signed by the Chair. | Decided | Open |
| 22 Jul 2026 | 26/00031 - Adoption of the Delivery of Local Government Efficiency (DOLGE) StrategyIt was RESOLVED that Cabinet: (a) Approved and adopted the Delivery of Local Government Efficiency (DOLGE) Strategy ;... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.