Resolved
RESOLVED that the contents of the report be noted.
Growth, Environment & Transport Cabinet Committee noted this item on Thursday 17 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contents of the report be noted.
From: Mike Whiting, Cabinet Member for Planning, Highways, Transport and Waste
Simon Jones – Director of Highways Transportation & Waste
To: Environment and Transport Cabinet Committee - 17th January 2019
Subject: Pothole Blitz Contract Management
Classification: Unrestricted (Exempt Appendix A)
Summary: This paper provides an overview of Pothole Blitz Contract.
The Pothole Blitz has delivered over £15 million in pothole repairs to damaged highway over the last 2 years.
It has been delivered on time and within budget and the contract has evolved to meet the changing needs year on year.
The next Pothole Blitz contract (2019 to 2020) has been procured and will provide savings across an increased supply chain.
Recommendation: The Cabinet Committee is asked to note the contents of the report.
1.0Introduction
1.1The Pothole Blitz Project Phase 2 (2017/2018) and Phase 3 (2018/2019) has been delivered through a contract procured in 2017.
1.2The contract covers individual pothole repairs, large patching repairs and associated sundry works.
1.3The contract (Phase 2 and 3) was an open tender process which procured the services of 6 SME contractors covering 2 districts each.
1.4The next phase of the Pothole Blitz (Phase 4) was procured in November 2018 under an open negotiated tender.
1.5A contract was awarded to 11 SME contractors distributed into three lots. The lots covered West, Mid, and East Kent with 3 or 4 contractors per lot.
1.6Each contractor has been allocated one district. Dartford and Gravesham have been combined for one contractor. 1.7 The increase to 11 contractors from the previous 6 gives the ability to significantly increase resources to meet the available funding and to deliver quickly.
2.0Phase 4 Pothole Blitz Contract - Management
2.2In order to ensure the effective management of the contract, several measures are available within the contract.
2.3Contract controls
The Contractor is required to comply with the performance measures set out in the contract specification.
Should the contractor breach any of the requirements in the contract, they are required to submit an improvement plan. Should the contractor fail three times against any of the contract requirements within a 12-month rolling period, we can terminate their contract.
A single significant Health and Safety breach can allow us to terminate the contract.
The contract allows contractors to move districts to cover the works of a suspended or terminated contractor.
2.4Key Performance Measures
The newly let contract includes 4 Key Performance Indicators to assist in measuring the success of the contract.
These include a monthly client satisfaction survey to report on the quality of the contractors / client relationship.
Failure of any of the Key Performance Measures are subject to the same sanctions as previously stipulated.
KPI performance will also be used as a pre-qualification requirement for any future contract.
2.5Lessons learnt
The new Key Performance Indicators were developed to tackle issues identified in the previous contract:
That the processes and timescales for certain types of repair were not aligned with the term contract service levels and that this had led to confusion for customers; That there were no measures in place to demonstrate success in the delivery of “right first-time” repairs or the delivery of corrective action for any defective works; That contractors who had been subject to notifications of contractual breaches on Phase 2 and 3 were still able to qualify to tender for future contracts without this being taken into consideration; and That there was no measure to recognise contractor collaboration or positive client relationships.
The use of contract notifications ensured that contractors understood the severity of any breaches and encouraged them to implement effective improvement plans.
During Phase 2, one contractor received 2 notifications and was in danger of receiving a 3rd. They replaced the delivery and supervision teams and as a result they became one of the highest performers.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Pothole Blitz Contract ManagementReport | 5 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.