17/00032 Local Growth Fund, Round Three and SELEP working group schemes

Agreed Executive 2 papers

Growth, Economic Development and Communities Cabinet Committee agreed this item on Wednesday 22 March 2017. Below is the council's own wording, with the papers it was decided on.

Item219

Resolved

Resolved that the Cabinet Committee endorse the proposed decision of the Cabinet Member for Economic Development to: (a) Accept Government grant funding of £12.95m capital to deliver the following schemes: · Fort Halstead in Sevenoaks (£1.53m) · Kent & Medway Engineering, Design, Growth and Enterprise (EDGE) Hub (£6.12m) · Leigh Flood Storage Area and East Peckham– Unlocking Growth (£4.636m) · SELEP Coastal Communities – Housing Led Economic Regeneration in Cliftonville West/Margate Central (£0.666m); (b) Enter into agreements for the transfer of the Local Growth Fund to the respective delivery organisation for the three schemes; and (c) Delegate to the Director of Economic Development and Director of Environment, Planning and Enforcement the authority to conclude arrangements to secure the recovery of administration costs associated with KCC’s management of the grant agreements.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Economic Development and Communities Cabinet Committee, 9 pages

From: Mark Dance, Cabinet Member for Economic Development

Barbara Cooper, Corporate Director, Growth, Environment and Transport

To: Growth, Economic Development and Communities Cabinet Committee – 22 March 2017

Decision No: 17/00032

Subject: Local Growth Fund, Round Three and SELEP working group schemes

Key Decision

Classification: Unrestricted

Past Pathway of Paper: N/A

Future Pathway of Paper: For Cabinet Member Decision

Electoral Division: Sevenoaks West, Sevenoaks South, Tonbridge, Canterbury South East, Margate and Cliftonville

Summary: In January 2017 the Government announced an allocation of £102m of local growth funding for the South East Local Enterprise Partnership (SELEP) for the delivery of a range of transport and business support related schemes. The Growth deal (Round 3) included the allocation of funding for Fort Halstead in Sevenoaks, Kent & Medway Engineering, Design, Growth and Enterprise (EDGE) Hub and Leigh Flood Storage Area schemes following the submission of outline business cases for each scheme to SELEP (http://www.southeastlep.com/growth-deal).

In addition to the above, a SELEP wide working group (Coastal Communities group) submitted a Housing Intervention Project as part of LGF Round 1 as a pan LEP project for housing interventions to be delivered in three coastal communities; Tendring, Thanet and Hastings.

This report explains the projects for which grant funding is sought, sets out KCC’s role and outlines the process that will be followed to secure the funding. It seeks the support of the Cabinet Committee for KCC to accept Government grant funding and transfer it to the respective delivery organisation, subject to approval of a full business case.

Recommendation(s):

The Growth, Economic Development and Communities Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Economic Development, as shown at Appendix A, to agree that the Council shall (subject to the completion of a full business case, satisfactory appraisal by an Independent Technical Evaluator and approval by SELEP Accountability Board): i) Accept Government grant funding of £12.95m capital to deliver the following schemes:

Fort Halstead in Sevenoaks (1.53m) Kent & Medway Engineering, Design, Growth and Enterprise (EDGE) Hub (6.12m) Leigh Flood Storage Area and East Peckham– Unlocking Growth (4.636m) SELEP Coastal Communities – Housing Led Economic Regeneration in Cliftonville West/Margate Central (£0.666m)

ii) Enter into agreements for the transfer of Local Growth Fund to the respective delivery organisation for the three schemes; and

iii) Delegate to the Director of Economic Development and Director of Environment, Planning and Enforcement the authority to conclude arrangements to secure the recovery of administration costs associated with KCC’s management of the grant agreements.

1. Introduction

1.1In the Growth Deal announcements in July 2014 (Round One) and January 2015 (Round Two), the Government allocated £482 million from the Local Growth Fund to capital projects across the South East Local Enterprise Partnership (SELEP) area.

1.2In January 2017 a further Growth Deal Extension was announced by Government following a SELEP Local Growth Fund Round Three submission.

1.3In total, through the three rounds, £104m Local Growth Fund has been allocated towards the delivery of 25 Highways and Transportation projects in Kent and £24m has been allocated to deliver 6 non-transport schemes in Kent.

1.4The Growth Deal extension (Round 3) included the allocation of funding for Fort Halstead in Sevenoaks, Kent & Medway Engineering, Design, Growth and Enterprise (EDGE) Hub and Leigh Flood Storage Area schemes following the submission of outline business cases for each scheme to SELEP (http://www.southeastlep.com/growth-deal).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
17/00032 Local Growth Fund, Round Three and SELEP working group schemesReport 9 pages DownloadRead as text
PDF
Item B5 Appendix AAppendix 2 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 17/00032 Local Growth Fund, Round Three and SELEP working group schemesThis decision
  2. 20/00083 - Local Growth Fund Round 3b Third Party Scheme - East Malling Advanced Technology Horticultural ZoneApproved
  3. 20/00058 - Local Growth Fund Round 3b Third Party Scheme - M2 Junction 5 Highway Improvement SchemeApproved
  4. 20/00064 - Local Growth Fund - Kent Strategic Congestion Management Programme - A2/A251 Junction Improvement SchemeApproved
  5. Local Transport Plan 4: Delivering Growth without GridlockApproved
  6. Local Transport Plan 4: Delivering Growth without GridlockApproved

More from Kent Growth, Economic Development and Communities Cabinet Committee

All decisions
MeetingDecisionOutcome
11 Nov 2025 Election of ChairRESOLVED that [name removed] be elected as Chair of the Growth, Economic Development and Communities Cabinet Committee. Decided Open
11 Nov 2025 Minutes of the meeting held on 11 September 2025RESOLVED that the minutes of the meeting held of 11 September 2025 were a correct record and they be signed by the Ch... Decided Open
11 Nov 2025 KMEF- Ambition 2- Widen opportunities and unlock talentRESOLVED to note the report. Noted Open
11 Nov 2025 Regional Energy Strategic PlanRESOLVED to note the report. Noted Open
11 Nov 2025 Decisions taken between Cabinet Committee Meetings- 25/00084It was agreed that consideration would be given to Member involvement in the reinstated Visitor Economy and Inward In... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies