20/00064 - Local Growth Fund - Kent Strategic Congestion Management Programme - A2/A251 Junction Improvement Scheme

Approved Executive 3 papers

Growth, Environment & Transport Cabinet Committee approved this item on Friday 17 July 2020. Below is the council's own wording, with the papers it was decided on.

Item266

Resolved

RESOLVED that the proposed decision (20/00064) to be taken by the Cabinet Member for Highways & Transport to approve the progression of the A2/A251 Junction Improvement Scheme, and , in particular, to approve that: (a) Kent County Council act as the accountable body for the project, (b) Kent County Council enter into a Local Growth Fund (LGF) funding agreement, (c) Kent County Council progress all statutory approvals or consents required for the scheme, (d) Kent County Council progress with the necessary land acquisitions required to deliver the scheme, (e) Kent County Council carry out public engagement on the scheme, (f) Kent County Council enter into construction contracts as necessary for the delivery of the scheme; and (g) The Corporate Director for Growth, Environment & Transport, under the Officer Scheme of Delegations and in consultation with the Corporate Director for Finance and Procurement, to enter into relevant legal agreements and take other actions necessary to implement this decision, be endorsed.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 6 pages

From: Michael Payne, Cabinet Member for Highways and Transport

Barbara Cooper, Corporate Director of Growth, Environment & Transport

To: Environment & Transport Cabinet Committee – 17 July 2020

Decision No: 20/00064

Subject: Local Growth Fund– Kent Strategic Congestion Management Programme – A2/A251 Junction Improvement Scheme

Classification: Unrestricted

Past Pathway of Paper: None

Future Pathway of Paper: Key decision sign off by Cabinet Member

Electoral Division: Faversham

Summary: In the original Growth Deal announcement in July 2014; KCC secured £4.8m for the delivery of the Kent Strategic Congestion Management Programme (KSCMP) in order to deliver schemes throughout the County to reduce the impact of increasing vehicular traffic.

The A2/A251 junction improvement scheme is proposed to be brought forwards as part of the KSCMP and a business case for the remaining £500k of the £4.8m programme is due to be considered by SELEP Accountability Board on 3rd July 2020.

The A2/A251 priority junction provides the primary access for Faversham and eastern Swale to the strategic road network. The junction caters for significant volumes of traffic and is currently operating over capacity in peak periods with serious levels of congestion and delay. This is a constraint to key strategic housing allocations in the Faversham area and to the economic wellbeing of the town.

The proposed scheme replaces the existing priority junction arrangement with a new signalised junction, which will include a controlled pedestrian crossing across the A2 eastern arm.

A key decision is required to allow KCC to progress with the next stages of scheme delivery; including negotiations with Kent Fire and Rescue Service and The Abbey School regarding small areas of land required to deliver the scheme, pursuing the Utility works and entering into a construction contract. This is required prior to the LGF business case sign off to ensure that the £500k LGF contribution can be spent within the Growth Deal period (prior to March 2021).

Recommendation(s):

The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to approve the progression, via KCC’s Local Growth Fund arrangements, for the A2/A251 Junction Improvement Scheme; allowing it to progress to the next stages of development and delivery.Specifically this comprises approval for:

i) KCC to act as the accountable body for the project;

ii) KCC to enter into a Local Growth Fund (LGF) funding agreement;

iii) KCC to progress all statutory approvals or consents required for the scheme;

iv) KCC to progress with the necessary land acquisitions required to deliver the scheme;

v) KCC to carry out public engagement on the scheme;

vi) KCC to enter into construction contracts as necessary for the delivery of the scheme; and

vii) The Corporate Director for Growth, Environment & Transport, under the Officer Scheme of Delegations and in consultation with the Corporate Director for Finance and Procurement, to enter into relevant legal agreements and take other actions necessary to implement this decision.

1. Introduction

1.1In the Growth Deal announcements in July 2014 (Round One), January 2015 (Round Two) and February 2017 (Round Three), the Government allocated £570 million from the Local Growth Fund to capital projects across the South East Local Enterprise Partnership (SELEP) area.

1.2In total, through the three rounds, £128m Local Growth Fund was allocated towards the delivery of 25 Highways and Transportation projects and 6 non- transport projects in Kent.

1.3Through the Round One Growth Deal announcement; KCC secured £4.8m for the delivery of the Kent Strategic Congestion Management Programme (KSCMP) in order to deliver schemes throughout the County to reduce the impact of increasing vehicular traffic.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20/00064: Local Growth Fund: Kent Strategic Congestion Management Programme: A2/A251 Junction Improvement SchemeReport 6 pages DownloadRead as text
PDF
Item 12: Appendix A: 20-00064: PRODAppendix 2 pages Download
PDF
Item 12: SUPPLEMENTARY: A2-A251 Faversham junction improvements EQIASupplementary 6 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 20/00064 - Local Growth Fund - Kent Strategic Congestion Management Programme - A2/A251 Junction Improvement SchemeThis decision
  2. 20/00083 - Local Growth Fund Round 3b Third Party Scheme - East Malling Advanced Technology Horticultural ZoneApproved
  3. 20/00058 - Local Growth Fund Round 3b Third Party Scheme - M2 Junction 5 Highway Improvement SchemeApproved
  4. Local Transport Plan 4: Delivering Growth without GridlockApproved
  5. Local Transport Plan 4: Delivering Growth without GridlockApproved
  6. 17/00032 Local Growth Fund, Round Three and SELEP working group schemesAgreed

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies