Commissioning Primary and Secondary Capacity in Ebbsfleet, Dartford

Agreed Executive 3 papers

Children, Young People and Education Cabinet Committee agreed this item on Friday 13 October 2017. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

RESOLVED that the decision proposed to be taken by the Cabinet Member for Children, Young People and Education, to: i. Commence a Free School Presumption Competition process in order to seek applications from potential sponsors to run a new Secondary School in Dartford, within the Alkerden development on Eastern Quarry, which forms part of the Ebbsfleet Garden City; ii. Commence a Free School Presumption Competition process in order to seek applications from potential sponsors to run a new 2FE Primary School in Dartford, within the Ebbsfleet Green development, which forms part of the Ebbsfleet Garden City; iii. Allocate £2.5m from the Basic Need Capital Programme Budget to fund the provision of the second FE of the proposed 2FE Primary School on Ebbsfleet Green; iv. Authorise the Director of Infrastructure in consultation with General Counsel to enter into any necessary contracts and agreements on behalf of the County Council; and v. Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts. Variations to contract value to be no more than 10% above the capital funding agreed by the Cabinet Member without requiring a new Record of Decision, be endorsed.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Children, Young People and Education Cabinet Committee, 8 pages

From: Roger Gough, Cabinet Member for Children, Young People and Education

Patrick Leeson, Corporate Director for Children, Young People and Education

To: Children’s, Young People and Education Cabinet Committee – 13 October 2017

Subject: Commissioning Primary and Secondary Capacity in Ebbsfleet, Dartford

Classification: Unrestricted

Future Pathway of Paper: Cabinet Member decision

Electoral Division: Swanscombe and Greenhithe – Peter Harman

Summary: This report sets out the need for a new Secondary School of up to 8 forms of entry (FE) and a new 2FE Primary School in Dartford and requests endorsement to commence Free School Presumption Competition processes to seek sponsors to run the new schools. This report also requests endorsement for the Cabinet Member’s decision to allocate the funding for the building of the second form of entry of the new 2FE Primary School.

Recommendation(s):

The Children’s Young People and Education Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Children, Young People and Education on the decision to:

(i) Commence a Free School Presumption Competition process in order to seek applications from potential sponsors to run a new Secondary School in Dartford, within the Alkerden development on Eastern Quarry, which forms part of the Ebbsfleet Garden City.

(ii) Commence a Free School Presumption Competition process in order to seek applications from potential sponsors to run a new 2FE Primary School in Dartford, within the Ebbsfleet Green development, which forms part of the Ebbsfleet Garden City.

(iii) Allocate £2.5m from the Basic Need Capital Programme Budget to fund the provision of the second FE of the proposed 2FE Primary School on Ebbsfleet Green.

(iv) Authorise the Director of Infrastructure in consultation with General Counsel to enter into any necessary contracts and agreements on behalf of the County Council. (v) Authorise the Director of Infrastructure to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts. Variations to contract value to be no more than 10% above the capital funding agreed by the Cabinet Member without requiring a new Record of Decision.

1. Introduction

1.1The need for new Secondary School provision to meet demand arising from the Ebbsfleet Garden City development was identified during the original planning of the City and has been highlighted in recent versions of the KCC Commissioning Plan for Education Provision, including the latest 2017-21 version of the Plan. More specifically the school is anticipated to accommodate pupils who are residents of any of the three villages on Eastern Quarry or of the Ebbsfleet Green development. Based on current housing trajectories for those developments, it is anticipated the first four forms of entry will be required by September 2021.

1.2The need for new Primary School provision to meet demand arising from the Ebbsfleet Garden City development was identified during the original planning of the City and has been highlighted in recent versions of the Commissioning Plan for Education Provision, including the latest 2017-21 version of the Plan. More specifically the school is anticipated to accommodate pupils who are residents of the Ebbsfleet Green development. Based on current housing trajectories, it is anticipated the first form of entry will be required by September 2020.

1.3Regardless of the situation in respect of the ESFA’s Free School Wave application process, the onus is on the local authority to run competitions outside of any Wave, as both schools will be funded either wholly through developer contribution or through a mixture of Local Authority Basic Need funding and developer contribution.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Commissioning Primary and Secondary Capacity in Ebbsfleet, DartfordReport 8 pages DownloadRead as text
PDF
Item 8: Appendix 1 PRoD: Free School Presumptions, EbbsfleetAppendix 2 pages Download
PDF
Item 8: Appendix 2: MAP Alkerden and Ebbsfleet school sitesAppendix 1 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Commissioning Primary and Secondary Capacity in Ebbsfleet, DartfordThis decision
  2. The Appointment of a representative to attend meetings of the Kent and Medway Primary Care Commissioning GroupNoted
  3. The appointment of a representative to attend meetings of the Kent and Medway Primary Care Commissioning GroupDecided
  4. Primary Commissioning in Gravesham DistrictDecided
  5. Primary Commissioning - Swale DistrictDecided
  6. Primary Commissioning and relocation of Special Schools (Special School Review)- Thanet DistrictDecided

More from Kent Children, Young People and Education Cabinet Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Minutes of the meeting held on 12 May 2026RESOLVED that the minutes of the meeting held on 12 May 2026 were a correct record. Decided Open
14 Jul 2026 Verbal Update by Cabinet MembersRESOLVED that the verbal updates be noted. Noted Open
14 Jul 2026 Performance MonitoringRESOLVED that the report be noted. Noted Open
14 Jul 2026 26/00042 - Proposed Expansion of Oakwood Park Grammar SchoolRESOLVED that the Committee considered and endorsed the proposed decision Decided Open
14 Jul 2026 26/00043 - Expert at Hands (EaH) and Local Authority (LA) Special Education Needs & Disability (SEND) Transformation GrantRESOLVED that the Committee considered and endorsed the proposed decision Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies