RESOLVED that the Education Cabinet Committee endorses the proposal to: a) increase capacity for September 2013 by adding temporary places in Year R at the following schools: i. 30 places at Bromstone Primary School ii. 30 places at Newington Community Primary School and Nursery; b) consult on the permanent enlargement of Bromstone Primary School, Newington Community Primary School and Nursery and Cliftonville Primary School from September 2014; and c) consult on the relocation of Laleham /Gap Special School from its current site to a new site at Westwood Cross.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
By: Patrick Leeson, Corporate Director, Education, Learning and Skills
To: Education Committee, 19 March 2013
Subject Primary Commissioning and relocation of Special Schools (Special School Review)– Thanet District
Classification: Unrestricted
Summary: This report updates Members of arrangements in place to ensure sufficient school places are available in Thanet, and seeks the views of the Education Committee on proposals to commission additional provision. In addition, it updates Members on the planned relocation of Laleham/Gap Special School.
Recommendations: The Education Committee is asked to endorse proposals to
a) Increase capacity for September 2013 by adding temporary places in Year R at the following schools: 30 places at Bromstone Primary School 30 places at Newington Community Primary School and Nursery
b) Consult on the permanent enlargement of Bromstone Primary School, Newington Community Primary School and Nursery and Cliftonville Primary School from September 2014
c) Consult on the relocation of Laleham/Gap Special School from its current site to a new site at Westwood Cross.
1. Introduction 1.1 The Thanet section of Kent’s “Commissioning Plan for Education Provision 2012-2017” indicates a need to add a significant number of school places in Thanet to manage the predicted increase in numbers of children. There is currently pressure on places in Margate and Ramsgate and this pressure is expected to increase. This has been brought about by both the rise in the birth rate and the unexpected number of families moving into the area.
1.2The pressure on places has been managed through temporary expansion for September 2012, adding 90 places in Year R (30 at Newlands Primary School, 30 at Callis Grange Primary School, 15 at Northdown and 15 at Palm Bay as outlined in the 12 September 2012 report to Education Cabinet Committee. It was also agreed with headteachers that they would admit over their PAN in exceptional cases. Consultation on the permanent expansion of Palm Bay Primary School was undertaken and a public notice was issued on 8 February on the proposal to expand the school from 1.5 FE to 2 FE. The Local Authority has worked closely with The Kemnal Trust in regard to the permanent expansion of Northdown Primary School from 1.5 FE to 2 FE. 2. Primary Proposals 2.1 Bromstone Primary School It is proposed to consult on the permanent expansion of Bromstone Primary School from 2 FE to 3 FE from September 2014 with a one year temporary expansion from September 2013. The school is in the process of converting to an Academy from 1 April 2013. a. Capital: The school would require some remodelling of existing accommodation to provide 3 Year R classes for September 2013 at an estimated cost of £95k. The total cost of providing permanent accommodation is estimated at £2m.
b. Revenue: The school will receive Growth funding for a maximum of three years to provide protection on the increased Year R admission number of 90 should pupil numbers fall short of this. The school will receive £6k for each additional class opened as a result of the expansion towards the cost of the non-staffing resources needed to set the class room up.
c. Human: The school will appoint additional teaching and support staff at the appropriate time. 2.2 Newington Primary School & Nursery It is proposed to consult on the permanent expansion of Newington Primary School & Nursery from 2 FE to 3 FE from September 2014 with a one year temporary expansion from September 2013. a. Capital: Accommodation will need to be provided for December 2013 with an estimated cost £400k. It is planned that the accommodation will be phased with the Early Years/Key Stage 1 accommodation provided as the first phase. The estimated cost of the second phase which would be required for September 2014 is £800k.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.