Resolved
RESOLVED that the verbal updates be noted, with thanks.
Growth, Environment & Transport Cabinet Committee noted this item on Thursday 30 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the verbal updates be noted, with thanks.
From: Matthew Balfour, Cabinet Member for Planning, Highways, Transport and Waste
To: Environment & Transport Cabinet Committee – 30 November 2017
Decision No: N/A
Subject: Cabinet Member – Written Updates
Classification: For Information
Past Pathway of Paper: N/A
Future Pathway of Paper: N/A
Electoral Division: Countywide
Summary: This paper provides an update to Members of the Environment and Transport Cabinet Committee on the major roads programme, KCC’s response to Highways England’s consultation on its proposed improvement to Junction 5 of the M2, lorry parking and the South East rail franchise.
Recommendation(s): The Cabinet Committee is asked to note the report.
1. Introduction
1.1This paper provides an provides an update to Members of the Environment and Transport Cabinet Committee on the major roads programme, KCC’s response to Highways England’s consultation on its proposed improvement to Junction 5 of the M2, lorry parking and the South East rail franchise.
2. Road Improvement Schemes Update
Current KCC Major Capital Programme
2.1Good progress has been made on the Major Capital Programme. Highlights include:
Rathmore Road, Gravesend is on track to finish on site in November 2017; Hermitage Lane improvement scheme, Maidstone, is on track to finish in November 2017; Jackson Civil Engineering has been awarded the contract to construct the A226 London Road/St. Clements Way scheme, Dartford, with work due to start in January 2018; The design of the A28 Chart Rd, Ashford, widening scheme is also well underway and Jackson Civil Engineering is on target to construct the scheme, commencing January 2018, subject to the Public Inquiry, which is due to start on 21November (as a result of the CPO); The preparation of Planning Application for the Sturry Link Road scheme is well underway and it is intended to submit an Application to KCC in December 2017; and Design of A2500 Lower Road/Barton Hill roundabout, Swale is well underway. With the very good news that our bid to the DfT was successful for the Lower Road widening, it is intended to construct both schemes under the same contract. Details of the delivery programme are being finalised, with construction due to start in 2018/19.
Bids for new Transport Schemes
2.2Both bids to the DfT’s National Productivity Investment Fund, NPIF, were successful:
Upgrade of 2 roundabouts on A249 at Kent Medical Campus, Maidstone A2500 Lower Road widening, Swale
2.3The M20 J7 signalisation bid to the Highways England’s Growth and Housing Fund, will be recommended by HE to pass through to the next stage of the bidding process.
2.4Two Expressions of Interest (see below) have been made by KCC to the DCLG’s Housing Infrastructure Fund (Forward Funding Schemes) with an announcement of those passing to the next stage anticipated on or around the Autumn Statement:
Physical Infrastructure for Otterpool Park, Shepway e.g. roads and rail improvements Highway infrastructure, Swale
2.5KCC has endorsed a number of district bids to DCLG’s Housing Infrastructure Fund (Marginal Viability Schemes) including new highway infrastructure in Thanet and Dover. Announcement of successful bids is anticipated on or around the Autumn Statement:
Other Transport Schemes
2.6Highways England are due to start construction of the new junction M20 J10a early 2018.
3. Junction 5 (M2) Consultation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Verbal updatesReport | 5 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies