Task & Finish Group Review of Future Commissioning of Soft Landscape Service
DecidedExecutive1 paper
Growth, Environment & Transport Cabinet Committee decided this item on Thursday 30 November 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Cabinet Member for Planning, Highways, Transport and Waste endorse the proposed decision for the Highways, Transportation and Waste team to continue supporting individual local councils who express an interest and to ensure that opportunities continue to remain available for the delivery of soft landscape service at local level.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 13 pages
From: Roger Wilkin, Director of Highways, Transportation & Waste
To: Environment & Transport Cabinet Committee – 30 November 2017
Subject: Task & Finish Group Review of Future Commissioning of Soft Landscape Service
Key Decision: Non Key Decision
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: Cabinet Member Decision
Electoral Division: Countywide service - All electoral divisions
Summary: At the meeting on 4 December 2015, this Cabinet Committee agreed to set up a Task & Finish Group to review options for the future commissioning of the soft landscape works service. The Task & Finish Group’s preferred approach was to to explore devolution of discretionary services to local councils. On 11 March 2016 the Cabinet Committee decided that Highways Transportation & Waste were to lead or assist with a series of workshops addressing the devolution of the soft landscape service to local councils. Ten workshops were held across Kent. Of the 49 parish councils which initially expressed an interest in devolution; 7 have subsequently taken on the service however, in the same period two districts councils have handed the service back.
Recommendation: The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Planning, Highways. Transport and Waste on the proposed decision for Highways Transportation & Waste to continue supporting individual local councils who express an interest and to ensure that opportunities continue to remain available for the delivery of soft landscape services at a local level.
1. Introduction
1.1At the 4 December 2015 Environment and Transport Cabinet Committee (ETCC) meeting Members agreed to set up a Task & Finish Group (T&FG) to review and make recommendations for the future commissioning of the soft landscape works service. The T&FG met on four occasions to consider the draft Diagnostic Report and the five proposed service options. (See Appendix A.)
1.2The T&FG’s preferred approach was to explore devolution of soft landscape services (mainly the discretionary services of urban grass, shrubs and hedges) to parishes and town councils while recognising the need to meet the MTFP savings target of £380k for 2017/18 and 2018/19. Subsequently HT&W lead on a series of workshops addressing devolution of the soft landscape service to local councils. This paper provides an update on the workshops held and the interest expressed so far.
2. The report
2.1The concept of local councils undertaking soft landscape works on behalf of KCC is not new and a number of councils had already taken up this option in the past (see Appendix B).
2.2However, it was felt that the devolution opportunity required wider dissemination to stimulate interest and HT&W worked with the Kent Association of Local Councils (KALC) to deliver six presentations. This was supplemented by four additional KCC countywide parish seminars and a further meeting with seven Swale parish councils (See Appendix C).
2.3Approximately 15 - 20 people attended each of the KALC area committee presentations and 124 parish representatives attended the four additional KCC parish seminars. Representatives from seven parishes attended the special Swale meeting. A number of representatives attended both the KALC and KCC seminars.
2.4Since the workshops took place 30 parishes and town councils in the west of the county and 19 parishes and town councils in the east have expressed specific interest in a devolved service. Interested local councils received detailed maps and schedules identifying KCC grass, shrubs and hedges within their boundaries with the measurements for each. The combined costs for this service in the 49 councils totals £94,613.38 out of a budget of £908,600 (this is the revised countywide budget allocation after meeting the 2017/18 MTFP savings). See Appendix D for a summary of interested parishes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.