Growth, Environment & Transport Cabinet Committee decided this item on Thursday 17 January 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the proposed decision (18/00073) to be taken by the Cabinet Member for Planning, highways, Transport and Waste on the revised Thanet Transport Strategy for subsequent consideration through the Thanet Local Plan examination process, be endorsed.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 5 pages
From: Mike Whiting, Cabinet Member for Planning, Highways, Transport and Waste
Barbara Cooper, Corporate Director of Growth, Environment and Transport
To: Environment and Transport Cabinet Committee – 17th January 2019
Subject: Thanet Transport Strategy
Key Decision: 18/00073
Classification: Unrestricted
Past Pathway of Paper: Thanet Joint Transportation Board
Future Pathway of Paper: N/A
Electoral Division: All Thanet District Divisions
Summary: The report sets out an overview of the proposed changes to the revised draft Thanet District Transport Strategy and its progress to date.
Recommendation(s):
Cabinet Committee is asked to comment and endorse or make recommendations to the Cabinet Member for Planning, Highways, Transport and Waste on the revised Thanet Transport Strategy for subsequent consideration through the Thanet Local Plan examination process as shown at Appendix A.
1 Introduction
1.1The revised Thanet Transport Strategy (TTS) attached as Appendix A, has been jointly developed with Thanet District Council (TDC). This draft represents an updated version of the TTS document that was endorsed by the Environment and Transport Cabinet Committee in November 2017.
1.2It replaces the former Thanet Transport Plan (2005) and provides a framework of transport policy to the year 2031, to support planned growth within the Thanet District, in line with the emerging Thanet Local Plan (TLP).
1.3This revised TTS responds to a recent review of the TLP, which in turn followed the decision of TDC not to proceed with the former draft. A revised Local Plan document has since been produced, which was subsequently approved by TDC and submitted to the Planning Inspectorate for examination.
1.4In line with the above, the revised TTS has also been endorsed by Thanet District Council and submitted as a supporting document to the Local Plan examination. 2 Financial Implications
2.1The measures detailed in the TTS, including significant elements of road infrastructure, remain linked to the larger development allocations and therefore have potential sources of developer funding.
2.2KCC has requested further clarification from TDC in relation to the viability appraisal work undertaken to assess the financial headway available within the emerging site allocations. This will inform the Infrastructure Delivery Plan (IDP), which will evolve as the examination process progresses.
2.3It is anticipated that necessary highway infrastructure will be funded by development with no financial commitment being placed on KCC. Further viability and technical appraisal work will inform the specification and delivery of final infrastructure proposals.
2.4It is possible that TDC will seek to impose a CIL for certain elements of highway infrastructure to ensure that the strategy is funded in a financially equitable way across the district.
2.5It is expected that an element of external funding will be sought to encourage rapid delivery of housing/employment growth, which are typically subject to competitive bidding process as and when funding streams are announced.
3 Policy Framework
3.1The TTS meets the objectives of ‘Increasing Opportunities, Improving Outcomes: Kent County Council’s Strategic Statement (2015-2020)’ by assisting in the delivery of the following outcomes.
Supporting business growth by enabling access to jobs through improved transport links;
Assisting in the delivery of well-planned housing growth by maximising the delivery of onsite infrastructure and appropriate off-site highway improvements;
Protecting and enhancing Kent’s physical and natural environment, by managing air quality concerns through the delivery of managed growth and Improved access to local rural communities;
Helping children and young people have better physical and mental health and giving young people access to work, education and training opportunities through a package of new walking and cycling routes, including links to areas of public open space;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.