Growth, Environment & Transport Cabinet Committee decided this item on Tuesday 15 September 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED to endorse the proposed decision of the Cabinet Member for Highways and Transport to procure and to delegate authority to the Corporate Director for Growth, Environment and Transport to award and enter into appropriate contractual arrangements for the provision of road asset renewal services including any potential extension periods in accordance with the expectations set out in the report.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 4 pages
From: Michael Payne Cabinet Member, Highways and Transport
Simon Jones, Director of Highways, Transportation & Waste
To: Environment & Transport Cabinet Committee Meeting – 15th September 2020.
Subject: Road Asset Renewal Contract 2021
Key decision: Yes
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: Cabinet Member Decision
Electoral Division: All Divisions
Summary: The Road Asset Renewal Contract (RARC) is currently delivered by Eurovia and expires on 31st December 2020. A replacement contract will be required to be procured prior to the end date. A Key Decision is required to award the contract/s for this service as the value exceeds £1m.
Recommendation(s): The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to procure and delegate authority to the Corporate Director for Growth, Environment and Transport to award and enter into appropriate contractual arrangements for the provision of Road Asset Renewal Services including any potential extension periods in accordance with the expectations set out in the report and shown at Appendix A..
1. Introduction
1.1The Road Asset Renewal Contract (RARC) is currently delivered by Eurovia and expires on 31st December 2020. Due to a higher level of funding spent through the contract which included unforeseen Brexit works, there is no scope to invoke the extension options detailed as the OJEU thresholds will be breached.
1.2A new contract will be required to be procured prior to 1st January 2021. This contract will allow for the prescribed works and services to be delivered for an initial 24-month period with potential extensions. 1.3 Under section 41 of the Highways Act 1980, as the local Highway Authority, the Council has a legal duty to maintain its respective sections of the highway network This duty includes responsibility for maintaining, managing and, where necessary, improving sections of the network. These services need to be commissioned externally to ensure the Council meets is statutory obligations and that service continuity is ensured.
1.4To effectively maintain our roads, footways and cycle tracks we undertake the delivery of renewal works to replace deteriorated areas which have reached the end of their useful life and preservation works to prolong the life of areas which are starting to deteriorate.
1.5The scope of work at each site varies but will include the following:
cold milling of the top layers of the road structure and repaving with an asphalt surface and/or binder course adjustments to covers and replacement of road markings and road studs where required. replacement of the traffic loops. road closures and night-time working with working restrictions in place with defined times.
2. Procurement Strategy
2.1Market engagement was conducted in May and identified a number of risks to be considered:
2.2KCC is committed to achieving net zero carbon emissions within the next decade and this will be a key focus of this contract, as we look to measure and benchmark accurate carbon emission baselines and explore ways that we can reduce and eliminate these.
2.3The services consist of multiple sites. There will be several phases of work throughout the contract period, with routine work carried out between January and November each year. The initial phases are planned as follows, subject to weather conditions:
Phase 1 – January to March 2021 Phase 2 – April to November 2021 Phase 3 – January to March 2022 Phase 4 – April to November 2022
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.