To: Environment and Transport Cabinet Committee – 15 September 2020
Subject: Risk Management: Growth, Environment and Transport Directorate
Classification: Unrestricted
Past Pathway of Paper: None
Future Pathway of Paper: None
Electoral Division: All
Summary: This paper presents the strategic risks relating to the Environment and Transport Cabinet Committee, comprising of three risks featuring on the Corporate Risk Register for which the Corporate Director is the designated ‘Risk Owner’ on behalf of the Corporate Management Team; plus a summary of key risks from within the directorate.
Recommendation(s): The Cabinet Committee is asked to consider and comment on the risks presented in this report.
1. Introduction
1.1Risk management is a key element of the Council’s internal control framework and the requirement to maintain risk registers ensures that potential risks that may prevent the Authority from achieving its objectives are identified and controlled.
1.2Directorate risks are reported to Cabinet Committees annually and contain strategic or cross-cutting risks that potentially affect several functions across the Growth, Environment & Transport directorate, and often have wider potential interdependencies with other services across the Council and external parties.
1.3Corporate Directors also lead or coordinate mitigating actions in conjunction with other Directors across the organisation to manage risks featuring on the Corporate Risk Register.
1 1.4 The majority of these risks, or at least aspects of them, will have been discussed in depth at the relevant Cabinet Committee(s) throughout the year, demonstrating that risk considerations are embedded within core business.
1.5The assessment scores given to individual risks help to prioritise risks in order to make clear which risks are most important to the Directorate and requires an understanding by senior managers of:
The likelihood of each threat occurring. The impact of each threat if it did occur.
The process adopted by KCC follows guidance provided to practitioners in the Management of Risk.
2. Growth, Environment and Transport led Corporate Risks
2.1Given the unprecedented nature of the Coronavirus pandemic, it is unsurprising that there is increased risk exposure across the directorate. Many of the impacts are still to be fully understood and could have both short and longer-term effects.
2.2The Corporate Director for the Growth, Environment and Transport directorate is the lead Director for three of the council’s corporate risks. A brief summary of changes over the past year are outlined below, with full details contained in the risk register attached at appendix 1. Due to the fluid nature of the Coronavirus situation, the risks will require regular review throughout the coming months.
Risk Risk Description Current Target Reference Score CRR0004 Simultaneous Emergency Response, 25 (High) 15 Resilience and Recovery (Medium) While there are robust controls in place for this risk, the level of risk was raised from 20 (High) to 25 (High) in July. This is to acknowledge the expected continued strain on council capacity and resources in the coming months, as we continue to run aspects of Covid-19 response and recovery in parallel, as well as standing up arrangements to prepare for the end of the UK/EU transition period in December 2020. This is in addition to any continuing work on the early 2020 flooding recovery and preparations for severe weather this winter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management: Growth, Environment and Transport DirectorateReport | 19 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.