21/00071 - Highway Emergency Tree Works Contract

Decided Executive 2 papers

Growth, Environment & Transport Cabinet Committee decided this item on Wednesday 8 September 2021. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

RESOLVED to endorse the proposed decision of the Cabinet Member for Highways and Transport to provide the Corporate Director for Growth, Environment and Transport with delegated authority to procure and enter into appropriate contractual arrangements for the provision of Emergency Tree Works, including any potential extension periods in accordance with the expectations set out in the report as shown in the Proposed Record of Decision.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 5 pages

From: David Brazier Cabinet Member for Highways and Transport

Simon Jones, Corporate Director of Growth, Environment and Transport

To: Environment & Transport Cabinet Committee Meeting – 8th September 2021.

Subject: Procurement and award of contract/s for Highway Emergency Tree Works Contract

Key decision: 21/00071

Classification: Unrestricted

Past Pathway of Paper: N/A

Future Pathway of Paper: Cabinet Member Decision

Electoral Division: All Districts.

Summary: The Highway Emergency Tree Works Contract is currently delivered by two contractors, one serving the West of the County and the second the East. These contracts expire on 31st October 2021. There are no further extension options, and a new contract is therefore required to be in place for 1st November 2021.A Key Decision is required to award the contract/s for this service as the value exceeds £1m.

Recommendation(s): The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Highways and Transport on the proposed decision to provide the Corporate Director for Growth, Environment and Transport with delegated authority to procure and enter into appropriate contractual arrangements for the provision of Emergency Tree Works, including any potential extension periods in accordance with the expectations set out in the report as shown at Appendix A.

1. Introduction

1.1The current Emergency Tree Works Contracts with Bridgland and Direct Enviro expire on 31st October 2021. There are no further extension options, and a new contract is therefore required to be in place for 1st November 2021.

1.2The original contract delivery model in 2016 was for three lots, but following one contractor entering administration, the work with the mid area of the county was split between the other two contractors. This has worked well for the remaining period. 1.3 The Council has a legal duty to keep roads and pavements clear of vegetation for safe passage of highway users. The main service areas comprise of clearing felled trees, most notable in adverse weather conditions. In order to ensure the Council meets its obligations the service will need to be commissioned.

1.4The requirement is for the provision of emergency response specialist tree surgery teams to attend at short notice on a 24/7 basis 365 days of the year. Emergency type response times will include 2-hour and 24-hour requirement. The service is used by all operational staff but also supports the highways out of hours emergency response service.

1.5There is no programmed works and work volumes are dictated by the weather and where emergency situations occur. This varies from year to year and is largely dependent on the prevailing weather and storm events.

1.6Demand for this service has grown over the course of the contract due to an increase in severe weather events as well as more instances of Ash Dieback across the County. The emergency at Walderslade Woods in February 2019 is an example of where this contract was used to clear the aftermath of one of these storm events.

2. Procurement Strategy

2.1Market engagement was conducted in May 2021 and identified a number of risks to be considered:

• Contract structure • Productivity • Performance management • Supply chain

2.2There are three options to deliver this service:

1. Split the contract into three lots (West, Mid and East) 2. Split the contract into two lots (current provision) 3. Countywide delivery

2.3Option 3 has been discounted due to the high-risk nature of this model. This is due to the distances involved in servicing the whole of Kent (attendance within two hours) and with demand fluctuated by weather events, there is no competition within the local market to demonstrate best value. As detailed within the market analysis the size of organisations is smaller. Furthermore, this option would not offer resilience to storm events.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
21/00071: Highway Emergency Tree Works ContractReport 5 pages DownloadRead as text
PDF
Emergency Tree Works Procurement PRODAppendix A 2 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 21/00071 - Highway Emergency Tree Works ContractThis decision
  2. 25/00089 - Highways Emergency Tree Works ContractAgreed

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies