Environment, Net Zero and Section 31 Public Sector Decarbonisation Scheme Update
NotedExecutive4 papers
Growth, Environment & Transport Cabinet Committee noted this item on Thursday 19 May 2022. Below is the council's own wording, with the papers it was decided on.
RESOLVED to: 1) note the considerable progress towards KCC Net Zero 2030 target achieved in 2021 despite the challenging operating environment; 2) discuss the changes to external funding that impacts on KCC’s ability to deliver the Net Zero by 2030 ambition and wider programme beyond 2023/24; 3) note the risks associated with the Net Zero and Public Sector Decarbonisation Scheme Programmes as outlined in section 6.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Growth, Environment & Transport Cabinet Committee, 13 pages
From: Susan Carey, Cabinet Member for Environment
Stephanie Holt-Castle, Director, Growth and Communities
To: Environment and Transport Cabinet Committee – 19 May 2022
Subject: Environment, Net Zero and Section 31 Public Sector Decarbonisation Scheme Update
Classification: Unrestricted
Past Pathway of Paper: n/a
Future Pathway of Paper: n/a
Electoral Division: County-wide
Summary: This paper is a summary of progress during 2021-22 towards the Kent wide and KCC environmental and net-zero targets and plans. It proposes an approach to re-evaluate the environmental priorities within the scope of the Strategic Reset Programme, recognising that access to finance is changing significantly and will start to impact on ‘environment’ staff resources in the medium term.
This paper also provides an update on the Public Sector Decarbonisation Scheme (PSDS) agreement with the Department of Business, Energy, and Industrial Strategy (BEIS) for a Section 31 grant of £20.6m to deliver a number of energy projects within the KCC estate and a further £1.2m for school site energy projects that was accepted in March 2021 and which will help KCC meet its target of achieving net-zero carbon emissions by 2030.
Recommendation(s):
1) The Cabinet Committee is asked to note the considerable progress towards KCC net- zero 2030 target achieved in 2021 despite the challenging operating environment.
2) The Cabinet Committee is asked to discuss the changes to external funding that impacts KCC’s ability to deliver the Net Zero by 2030 ambition and wider programme beyond 2023/24.
3) The Cabinet Committee is asked to note the risks associated with the Net Zero and Public Sector Decarbonisation Scheme Programmes as outlined in section 6.
1. Introduction to KCC Net Zero 2030
1.1KCC has a long-established environmental improvement programme, certified to the International Standard for Environmental Management ISO14001, which continues to demonstrate year-on-year progress in reducing KCC’s environmental impacts and most significantly reducing greenhouse gas (GHG) emissions by 73% since 2010. This lends credibility to KCC’s role as leader of the delivery of the Kent wide environmental and climate change strategies and plans, which requires significant partnership support to be successful.
1.2Recognising the Climate Emergency, in September 2020, the Cabinet Member for the Environment took the decision to set an ambitious target to reduce the direct emissions from KCC’s estate and operations to Net Zero by 2030, 20 years ahead of the UK Government’s target, delivered through a mix of KCC actions and offsetting. This is KCC’s organisational target and does not include emissions from commissioned and outsourced services (known as scope 3 emissions). An expanded baseline, which includes emissions data from KCC’s traded companies was established for 2019-20 and monitoring against this target is included in KCC’s published quarterly performance report.
1.3In addition to the monitoring of emissions from KCC’s estate and operations, the KCC environment programme seeks to ensure delivery of the commitments detailed in KCC’s Environment Policy and relevant aspects of the Kent wide strategies and plans that need to be taken account of or delivered by KCC services (see Appendix 1 for a full list). This ensures the programme reflects both the climate and ecological emergency, statutory requirements, pollution, and health concerns and seeks to address both climate mitigation and adaptation actions.
2. Policy Framework for KCC Net Zero 2030
2.1The environment is one of the five main Challenges set out in the Interim Strategic Plan which remains in place until May 2022. Tackling the climate emergency is identified as an urgent priority. ‘KCC’s role in achieving Kent’s environmental ambitions’ was additionally identified as one of four Strategic Policy Challenges in the December 2021 County Council Strategic Statement development update paper.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.