Resolved
RESOLVED to note the contents of the report.
Growth, Environment & Transport Cabinet Committee noted this item on Thursday 19 May 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the contents of the report.
From: David Brazier, Cabinet Member for Highways & Transport
Simon Jones, Corporate Director for Growth, Environment & Transport
To: Environment and Transport Cabinet Committee - 19 May 2022
Subject: Electric Vehicle Charging Infrastructure in Kent
Classification: Unrestricted
Past Pathway of report: NA
Future Pathway of report: NA
Electoral Division: All
Summary: This report provides an update regarding the current position of Electric Vehicle (EV) Charging Infrastructure across Kent. It follows up on the report brought to ETCC in November 2021.
Recommendation(s): The Cabinet Committee is asked to comment on and note the contents of the report.
1. Introduction
1.1This report gives a broad overview of the projects being delivered in Kent and outlines the next steps in response to the Government’s published UK electric vehicle infrastructure strategy that has been published at the end of March 2022.
2. Electric Vehicles Charging Infrastructure
2.1In March 2022, the Government published Taking Charge: Electric Vehicle (EV) infrastructure strategy. It sets out the vision for public charging across the UK and the role that they anticipate public and private sector partners to play in delivering this.
2.2The strategy looks ahead to 2030 and the planned ban on sales of new petrol and diesel vehicles. They state: By 2030, we expect there to be around 300,000 public chargepoints as a minimum in the UK, but there could potentially be more than double that number. (p4, Taking charge: the electric vehicle infrastructure strategy)
2.3The strategy acknowledges that the exact charging mix between high powered and slower chargers is unclear as the market is still developing. However, the Government intends to influence chargers where demand is highest and where it is difficult to install, such as on-street.
2.4We will transform local on-street charging by putting an obligation on local authorities (subject to consultation) to develop and implement local charging strategies to plan for the transition to a zero-emission vehicle fleet. These strategies should identify how to provide affordable, convenient charging for residents, businesses including fleets, and visitors without causing pavement disruptions that could discourage walking and cycling. (p8, Taking charge: the electric vehicle infrastructure strategy)
2.5There will likely be an obligation on Local Authorities (at Highway Authority Level) to publish a clear strategy as to how they intend to help meet the wider aims of the Government’s strategy for their areas.
Annex 1. Roles and responsibilities, Taking charge: the electric vehicle infrastructure strategy
2.6Alongside the publication of the strategy the Government has announced new funding that will be made available to Local Authorities to support this work including £500m Local EV Infrastructure Fund (LEVI).
2.7KCC is already doing a lot of work to provide public charging infrastructure and will be well placed to publish an official strategy when required. The programme of works being delivered currently is encompassed in the Kent & Medway Energy and Low Emission Strategy.
2.8All the projects in development and mentioned in this report leverage external funding, grants, and private sector investment – often giving an income back to the Local Authorities as landowners. This minimises up front financial risk and allows a long- term income generation while the technology and market develop.
2.9Anticipating EV Charger socket requirements in Kent. In 2018 KCC commissioned CENEX, a leading not for profit consultancy in the clean transport space, to forecast EV charger demand across Kent until 2028 for passenger vehicles. In light of recent technological advances, the 2030 ban on new petrol and diesel vehicles and the new companies moving into this space; KCC asked CENEX to update this report in 2021.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Electric Vehicle Charging Infrastructure in KentReport | 6 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.