Resolved
RESOLVED that the information set out in the report and in response to comments and questions be noted, with thanks.
Policy and Resources Cabinet Committee noted this item on Tuesday 11 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the information set out in the report and in response to comments and questions be noted, with thanks.
1.1The Council currently commissions Total Facilities Management (TFM) services with two providers, Amey and Skanska, for the KCC corporate landlord estate, and some statutory compliance for schools which are the responsibility of KCC. The Council also makes available waste services, cleaning, and catering services to schools through separate contracts, which are not part of the TFM service.
1.2The current TFM contracts were extended to 31 October 2022. A new facilities management delivery model has been implemented which includes one countywide hard FM contract (including statutory compliance, planned preventative maintenance, project services, helpdesk, handypersons, landscaping, and ground maintenance services) and multiple countywide soft FM contracts (including cleaning and feminine hygiene, waste, landscaping and pest control and reception and security).
2. Current TFM Performance (Contractual including Key Performance Indicators (KPIs))
2.1Overall Mid-Kent compliance performance (Amey) is shown in the table overleaf: Corporate Previous Landlord Dec- Jan- Feb- Mar- Apr- May- Performance Area 8 month (CLL) or 21 22 22 22 22 22 Average School Statutory Compliance CLL 97% 100% 99% 95% 99% 92% 98% Level Reactive Task CLL 97% 92% 91% 93% 95% 89% 94% Completion Performance Number of Repeat CLL 0 0 0 0 0 0 0 Requests Statutory Compliance School 97% 99% 99% 97% 92% 92% 100% Level Reactive Task School 99% 94% 96% 97% 98% 92% 97% Completion Performance
2.2Overall East-Kent compliance performance (Skanska) is shown in the table below:
Corporate Previous Landlord Dec- Jan- Feb- Mar- Apr- May Performance Area 8 month (CLL) or 21 22 22 22 22 -22 Average School Statutory Compliance 100 100 100 CLL 100% 99% 99% 99% Level % % % Reactive Task Completion 100 100 100 CLL 99% 99% 98% 97% Performance % % % Number of Repeat CLL 1 2 1 1 2 2 1 Requests Statutory Compliance 100 100 100 100 100 School 100% 99% Level % % % % % Reactive Task Completion 100 100 100 School 100% 99% 96% 98% Performance % % %
2.3Overall West-Kent compliance performance (Skanska) is shown in the table below:
Corporate Previous Landlord Dec- Jan- Feb- Mar- Apr May- Performance Area 8 month (CLL) or 21 22 22 22 -22 22 Average School 100 100 100 Statutory Compliance Level CLL 100% 99% 99% 99% % % % Reactive Task Completion 97 100 CLL 100% 99% 99% 99% 95% Performance % % Number of Repeat CLL 1 1 0 1 1 2 1 Requests 100 100 100 100 100 Statutory Compliance Level School 100% 99% % % % % % Reactive Task Completion 100 100 94 School 100% 99% 99% 99% Performance % % %
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Facilities Management UpdateReport | 7 pages | DownloadRead as text |
Follow Policy and Resources Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... | Decided | Open |
| 2 Jul 2026 | Local Outcomes FrameworkRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... | Approved | Open |
| 2 Jul 2026 | Work ProgrammeRESOLVED that the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.