Resolved
RESOLVED to note the report.
This report provides the Policy and Resources Cabinet Committee the bi-annual update on Kent County Council’s (KCC) Facilities Management (FM) arrangements to provide services across both the corporate and schools estate, for which KCC has responsibility. It includes an update on the performance of the current contract and changes over the last six months.
Recommendation(s):
The Policy and Resources Cabinet Committee is asked to note the report.
1. Introduction/Background
1.1On the 1 November 2022 the disaggregated new FM model came into effect across the Corporate Landlord (CLL) and school managed estate.
1.2The FM services have been split into contracts for:
• Hard FM contract – planned and reactive maintenance, statutory compliance, and overall helpdesk – delivered by Skanska. Across approximately 370 CLL buildings and 490 Schools.
• Cleaning and Feminine Hygiene contract – delivered by Churchills. Across approximately 271 CLL sites.
• Waste and Recycling – delivered by Countrystyle. Across approximately 187 CLL sites and 264 Schools.
• Landscape and Pest Control – delivered by Commercial Services Group (Landscape Services). Across approximately 387 sites for tree management CLL and Schools. 187 for grounds maintenance and 60 sites for Pest Control for Corporate Landlord sites.
• Security - delivered by Sight and Sound, Wards Security and Prestige - this service will be subject to a service review with new arrangements being put in place during 2024. Across approximately 235 CLL sites.
• Porterage, Reception and Post Room services – delivered in-house by KCC FM team.
1.3The current poor condition of the KCC estate, and historic lack of asset replacement and capital investment in buildings, continues to place increasing pressure on the delivery of FM services with FM services delivered to Warm Safe and Dry standard with this context.
1.4The key objectives for the FM service delivery arrangements are:
• FM service delivery standards should be consistent and responsive to service requirements and required standards.
• FM services should deliver value for money for Kent and ensure that the Council meets its statutory responsibilities.
2. Hard FM Performance (Contractual including Key Performance Indicators (KPIs))
2.1Key Performance Monitoring data outlined below focuses on the completion of planned, reactive and statutory tasks.
2.2Each month KCC and Skanska review the performance of the contract at the Governance group meetings.
2.3In April 2024, indexation was applied to the contract in line with the Consumer Price Index as outlined within the contract.
2.4Overall Planned Preventative Maintenance (PPM) tasks for the corporate and school managed estate are outlined below. The contractor shall ensure that Routine Maintenance for all systems and Assets except Critical Systems on the Routine Maintenance Schedule within the Performance Month are carried out within the relevant tolerances. These are outlined in Appendix A.
Month All PPM Tasks % Completion Statutory PPM Tasks % Completion January 2024 2550 99 659 96 February 2024 2756 98 714 97 March 2024 2857 99 621 99 April 2024 3284 98 790 98 May 2024 2931 98 664 97 June 2024 3266 98 629 96 • These figures demonstrate the high volume of PPM tasks that are completed as part of the fixed priced fee on a monthly basis across the estate.
• This data shows the level of planning required to maintain assets in a planned manner across the estate.
• Tasks which are completed late against the routine maintenance schedule, or where evidence of completion was not available in a timely manner, are failed, even though the site remains compliant with statutory requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SLA and Indicative ScenariosAppendix A | 5 pages | Download |
PDF |
Facilities Management Bi-Annual UpdateReport | 12 pages | DownloadRead as text |
Follow Policy and Resources Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting held on 6 May 2026RESOLVED that the minutes of the meeting held on 6 May 2026 were a correct record and that they be signed by the Chai... | Decided | Open |
| 2 Jul 2026 | Local Outcomes FrameworkRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | Budget Planning Process 2027-28 and Medium-Term Financial Plan (MTFP) UpdateRESOLVED that the report be noted. | Noted | Open |
| 2 Jul 2026 | 26/00032 - Adoption of the KCC Winning for Kent: Procurement with Purpose Policy 2026-2028RESOLVED that the Cabinet Committee endorses the proposed decision to: (a) Approve the adoption and implementation of... | Approved | Open |
| 2 Jul 2026 | Work ProgrammeRESOLVED that the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.