Resolved
RESOLVED to endorse the Cabinet Member for Environment on the proposed decision to deploy up to £878,000 of additional funding to cover the increase in costs including risk contingencies to complete the Kings Hill Solar Park project.
Growth, Environment & Transport Cabinet Committee decided this item on Tuesday 8 November 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to endorse the Cabinet Member for Environment on the proposed decision to deploy up to £878,000 of additional funding to cover the increase in costs including risk contingencies to complete the Kings Hill Solar Park project.
From: Susan Carey Cabinet Member for Environment
Simon Jones Corporate Director, Growth Environment and Transport
To: Environment and Transport Cabinet Committee – 8 November 2022
Subject: 22/00099 - Kings Hill Solar Park: Additional funding
Key decision: Expenditure over £1m
Classification: Part 1: Main Report Unrestricted Part 2: Exempt Appendix – Section 12a Local Government Act
Past Pathway of Paper: N / A
Future Pathway of Paper: For Cabinet Member Decision
Electoral Division: Malling Rural East
Summary: KCC is constructing a solar park at Kings Hill to provide a renewable energy source that will offset approximately 7% of KCC’s electricity needs following receipt of a major capital grant in March 2021, from the Public Sector Decarbonisation Scheme (see decision 21/00034 for further information).
Building works are well underway at the site, with a completion date of June 2023.
The project has, however, been impacted by a number of issues, which has increased the capital cost of the project to £5,044,000. This means that additional funding of up to £878,000 is needed to complete delivery of the project.
Offsetting these increased costs in the longer term is the fact that the solar panels will be capable of generating power over a 40-year period, an increase of 10 years from initial expectations. In addition, based on current energy costs the solar park is projected to save KCC £360,000 in its first year of operation, and an annual equivalent of £330,000 per year for the life of the park.
Overall, the business case for the project has improved since inception and the project will be beneficial to KCC into the future, both financially and from a carbon reduction perspective. However, if approved it does in the short term, add pressure to the current financial situation.
Recommendation: The Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Environment on the proposed decision to deploy up to £878,000 of additional funding to cover the increase in costs including risk contingencies to complete the Kings Hill Solar Park project as shown at Appendix A 1. Background
1.1In March 2021, KCC was awarded a grant of £20,643,000 from the Public Sector Decarbonisation Scheme (PSDS) to deliver a number of projects, including ultimately £3,465,000 to build the Kings Hill solar park. The grant conditions for the PSDS required funding to be spent by 31 March 2022, which was later extended to 30 June 2022 following lobbying from authorities in receipt of grant funding (see decision 21/00034 for further information).
1.2An urgent key decision (21/00034) was taken to accept the funding, acknowledging the risk of the demanding delivery deadline and risk of the PSDS grant being spent in that time. This decision was subsequently endorsed at the meeting of the Environment & Transport Cabinet Committee (ETCC) on 18 March 2021.
1.3The initial preferred site for the solar park was one of KCC’s closed landfill sites but the necessary remediation work would have meant the grant deadline condition would not have been met. Further work identified a disused pig farm at Kings Hill as a deliverable alternative site.
1.4Progress with the PSDS funding projects was provided at the ETCC on 29 June 2021.The Key decision on Kings Hill Solar Park (21/00109) to deploy funding whilst understanding the associated risks this could bring was taken as an urgent decision on 10 December 2021 and was reported to ETCC on 18 January 2022.
1.5The land at Kings Hill was acquired in March 2022 and initial works started on site in the same month. Members were last updated on progress in delivering the projects funded by the PSDS on 19 May 2022.
2. Kings Hill progress
2.1Building works are well under way at the site with a completion date of June 2023. Once completed, the solar park is projected to offset 633 tonnes of carbon per year, which equates to around 7% of KCC’s annual carbon emissions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
22/00099: Kings Hill Solar Park: Additional funding requirementDecisions | 6 pages | DownloadRead as text |
PDF |
Proposed Record of DecisionDecisions | 1 pages | Download |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.