Task Force Team – to build a plan to reduce storm overflows. The Storm Overflow Task Force “ONETEAM” ▪ The task force is a dedicated team that is central to Southern Water’s drive towards significantly reducing the use of storm overflows by 2030, and managing wastewater flows within catchments.
▪ The establishment of the task force indicates Southern Water’s commitment to set targets and is a highly important workstream within the business.
▪ The task force is responsible for delivering five pathfinder projects over the next two years. The task force will seek to establish strong partnerships to ensure their success. Our Pathfinders in Kent are:-
▪ Deal
▪ Swalecliffe
▪ Margate
▪ There are 3 main types of intervention to reduce flooding and storm overflow use.
▪ Weblink - Storm Overflows (southernwater.co.uk) 2 “Slow the Flow” trial on passive water butts installation
3 Slow the Flow door knock in Deal with Councillor Bond
4 Household & Non-Household SuDs Opportunities - Planters
5 SuDS Construction Details SuDS Construction Details Outline Approval – Tree Pit Outline Approval – Pocket Basin SuDS Construction Details SuDS Construction Details Outline Approval – Rain Outline Approval – Roadside Garden Build Out Rain Garden Much more - Connectivity Surveys, Sewer Level Monitors, Rain Gauges and Flow monitoring
8 Albert Rd – Deal Surface Water Enlargement
9 Great collaborative working with KCC Highways – Albert Rd gulley enlargement completed this year Works completed Working with Streetworks team in KCC on Traffic Management for MTS to complete the surveys. Golf Road WPS remedial works (1) ▪ Scope of works required to improve the resilience, safety and performance of Golf Road WPS agreed following Platinum Health Check and PathFinder reviews
▪ Works will be delivered by AFECO as Principal Designer and Principal Contractor – appointments and programme being generated for an anticipated start on site date in November
▪ Remedial works split into 6 areas to allow focus on key issues and allocate funding:
▪ AREA 1 – TRANSFER PUMPS incorporating chemical dosing area and rising main
▪ AREA 2 – STORM PUMPS incorporating storm station, screening, booster pumps and storm loop
▪ AREA 3 – COMPOUND incorporating building and documentation
▪ AREA 4 – MCC incorporating replacement of MCC and telemetry
▪ AREA 5 – MISCELLANEOUS incorporating lifting and labelling
▪ AREA 6 – GENERATOR incorporating review of size once other works complete / refurbishment 13 Golf Road WPS remedial works (2) ▪ Critical areas of work which will be primary focus are AREA 1 – TRANSFER PUMPS and AREA 2 – STORM PUMPS
▪ Both areas cover the critical works required to increase pass forward flow rates and improve storm control so the Permit conditions can be met (flows currently limited due to concerns over the integrity of the rising main)
▪ Documents drafted / in train for comment and approval ahead of start on site – new station control philosophy; ALM; plan for monitoring and remedials works / relining of rising main; CCP; programme and costs
▪ Other AREAS will be developed in parallel to optimise time on site
Start on site to implement Development of design Approvals process as much as possible and documentation ahead of mains work
14 What we are doing in Operations: - 1. What have we done at Swalecliffe Wastewater Treatment Works since November 2021. 2. Swalecliffe WTW Short Sea Outfall Replacement 3. Gorrell Tank Whitstable 4. We’ve taken action to reduce the impact of stormwater releases on Swalecliffe Brook
15 Meet the Team 17
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Storm Overflows, Pollution and Pathfinder Projects: Presentation by Southern WaterReport | 17 pages | DownloadRead as text |
Follow Kent Flood Risk and Water Management Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes of the meeting on 04.03.26RESOLVED that the minutes of the meeting held on 4 March 2026 were an accurate record and that they be signed by the ... | Decided | Open |
| 4 Mar 2026 | Minutes of the meeting on 29.10.2025RESOLVED that the minutes of the meeting held on 29 October 2025 were an accurate record and that they be signed by t... | Decided | Open |
| 4 Mar 2026 | KCC Severe Weather Response Activity ReportRESOLVED to note the verbal update on | Noted | Open |
| 4 Mar 2026 | Met Office- Introduction PresentationRESOLVED to note the Met Office Presentation | Noted | Open |
| 4 Mar 2026 | SGN - Introduction and Water Ingress into the Gas Network PresentationRESOLVED to note the Southern Gas Network (SGN) presentation | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.