Resolved
RESOLVED to agree the recommendations as outlined in the report.
Children, Young People and Education Cabinet Committee agreed this item on Tuesday 17 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to agree the recommendations as outlined in the report.
From: Rory Love, Cabinet Member for Education and Skills
Sarah Hammond, Corporate Director for Children, Young People and Education
To: Children’s, Young People and Education Cabinet Committee – 17 January 2023
Subject Expansion of Sir Roger Manwood’s School
Classification: Unrestricted
Decision Number: 23/00002
Past Pathway of Paper: None
Future Pathway of Paper: Cabinet Member Decision
Electoral Division: Sandwich
Summary: This report provides the Committee with the information regarding the expansion of Sir Roger Manwood’s School, Sandwich, and the proposal to pass over developer contributions secured by the County Council to assist in funding this.
Recommendation(s):
The Children’s, Young People and Education Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Education and Skills on the proposed decision to:
I. Agree a funding agreement between Kent County Council and Sir Roger Manwood’s School Trust be entered into to enable £2.1m (plus indexation) of developer contributions to be paid to the School as and when received by the Council.
II. Authorise the Director of Education in consultation with the General Counsel to enter into any necessary contracts / agreements on behalf of the County Council.
III. Authorise the Director of Education to be the nominated Authority Representative within the relevant agreements and to enter into variations as envisaged under the contracts.
1. Introduction
1.1Sir Roger Manwood’s School is a co-educational selective school in Sandwich. In 2015 the School’s Trustees increased the Published Admissions Number from 120 places per year group to 150 and has been self-funding remodelling of the School’s buildings to accommodate the additional pupils. 1.2 The Authority has not provided any funding from its Capital Programme to support the expansion of the School. To date financial support has been limited to £285k of developer contributions which the Authority received and passed on to the School to pay for works undertaken as part of its expansion.
1.3The School has a master plan in place which demonstrates how it will continue to remodel its facilities to address the pressure points created by admitting additional pupils. The plans demonstrate three phases of works. The Authority has sought developer contributions to support the School’s expansion from 4FE to 5FE, with agreements in place to the value of £2.1m (including the £285k mentioned above) (listed in Appendix A). In line with the CIL Regulations that applied at the time, these contributions name the School and can only be used to support expansion here. They also refer to phases of delivery, again because the CIL Regulations at the time restricted the Authority to utilising no more than five obligations to a project.
1.4Dover District has seen secondary school rolls rising for several years. In the non-selective sector this increase has been absorbed within existing capacity. However, in the selective sector Dover Girls’ Grammar School, Dover Grammar School for Boys and Sir Roger Manwood’s School have all increased their Published Admissions Numbers and have admitted further pupils. Consequently, the Authority’s forecasts (Figure 1) indicate only a small deficit of Year 7 places in forthcoming years. This would not be the case had Sir Roger Manwood’s not increased by 1FE.
Figure 1: Secondary - Year 7 surplus/deficit capacity if no further action is taken 2021-22 (A)
2022-23 (F)
2023-24 (F)
2024-25 (F)
2025-26 (F)
2026-27 (F)
2027-28 (F)
2028-29 (F)
2029-30 (F)
2030-31 (F)
2031-32 (F) capacity
capacity 2021-22
2031-32
Dover 440 2 3 -6 -6 6 -6 -1 -5 4 27 31 440 Selective
2. The Proposal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 1 pages | Download |
PDF |
Expansion of Sir Roger Manwood's SchoolReport | 6 pages | DownloadRead as text |
PDF |
PRODReport | 3 pages | Download |
Follow Children, Young People and Education Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Minutes of the meeting held on 12 May 2026RESOLVED that the minutes of the meeting held on 12 May 2026 were a correct record. | Decided | Open |
| 14 Jul 2026 | Verbal Update by Cabinet MembersRESOLVED that the verbal updates be noted. | Noted | Open |
| 14 Jul 2026 | Performance MonitoringRESOLVED that the report be noted. | Noted | Open |
| 14 Jul 2026 | 26/00042 - Proposed Expansion of Oakwood Park Grammar SchoolRESOLVED that the Committee considered and endorsed the proposed decision | Decided | Open |
| 14 Jul 2026 | 26/00043 - Expert at Hands (EaH) and Local Authority (LA) Special Education Needs & Disability (SEND) Transformation GrantRESOLVED that the Committee considered and endorsed the proposed decision | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.