Resolved
RESOLVED to agree the recommendations as outlined in the report.
Children, Young People and Education Cabinet Committee agreed this item on Tuesday 17 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to agree the recommendations as outlined in the report.
From: Rory Love, Cabinet Member for Education and Skills
Sarah Hammond, Corporate Director of Children, Young People and Education
To: Children’s and Young People’s Cabinet Committee – 17 January 2023.
Subject: Proposal to rebuild and expand Teynham Parochial CEP Primary School from 210 places to 420 places, increasing the published admission number (PAN) from 30 to 60 for September 2025.
Decision Number and Title Proposal to rebuild and expand Teynham Parochial CEP Primary School from 210 places to 420 places, increasing the published admission number (PAN) from 30 to 60 for September 2025.
Key Decision Yes: It involves expenditure or savings of over £1m Public Notice required
Classification: Unrestricted
Past Pathway of report: N/A
Future Pathway of report: Cabinet member Decision
Electoral Division: Swale East - Rich Lehmann
Summary: This report sets out the case for the rebuilding and expansion of Teynham Parochial CEP primary school from a PAN of 30 to 60. This will ensure there are sufficient primary school places in Teynham to meet the need of new pupils from the new housing developments in Teynham. The Proposal will be reported back to Children’s, Young People and Education Cabinet Committee in advance of a further decision on the allocation of Capital budget and approval to issue a public notice.
Recommendation(s): The Children’s, Young People and Education Cabinet Committee is asked to consider and endorse or make recommendations to the Cabinet Member for Education and Skills on the proposed decision to rebuild and permanently expand Teynham Parochial CEP primary school from 210 places to 420 places, increasing the published admission number (PAN) from 30 to 60 for Year R entry in September 2025
The Cabinet Member for Education and Skills is asked to agree to (i) the proposal to rebuild and expand Teynham Parochial CEP Primary School from 210 to 420 places, increasing the published admission number (PAN) from 30 to 60 for September 2025 (1FE to 2FE) from September 2025.
This decision is conditional upon planning permission being granted and a further decision on the allocation of Capital budget and approval to issue a public notice.
1. Introduction
1.1Kent County Council (KCC) as the Local Authority has a duty to ensure sufficient school places are available. The County Council’s commissioning plan for Education Provision in Kent 2022-2026 is a five-year rolling plan which is updated annually. It sets out our future plans as Strategic Commissioner of Education Provision across all types and phases of education in Kent. A copy of the plan can be viewed from this link:
https://www.kent.gov.uk/education-and-children/schools/education- provision/education-provision-plan
1.2The Commissioning Plan 2016-2020 identified there would be a need to expand Teynham Parochial CEP Primary School when new housing came forward in Teynham. This would ensure there were sufficient school places for families in Teynham and the surrounding area. The expansion of Teynham Primary School aligns with the objectives of Swale Borough Council’s Local Plan which was adopted in 2017.
2. The Proposal
2.1We are proposing to permanently increase the size of the school by 1FE to meet the primary school pupil needs in Teynham and it is proposed to do this through rebuilding and expanding the school to meet increasing demand arising from new housing planned for the local area.
2.2A feasibility study was commissioned in 2019 to look at the options of expanding Teynham Primary School. The feasibility gave 3 options on the expansion of the school including options to build a standalone classroom block with the upgrade of the current school building and an additional option to rebuild the school as a new 2FE school due to the poor condition of the current building. A further condition report was requested to look into the costs of refurbishing the current building and the risks associated with expansion of the current building. The full report can be found at appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 4 pages | Download |
PDF |
Appendix 2Appendix 2 | 3 pages | Download |
PDF |
Teynham Primary School: Expansion of Teynham Primary School by 1FEReport | 7 pages | DownloadRead as text |
Follow Children, Young People and Education Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Minutes of the meeting held on 12 May 2026RESOLVED that the minutes of the meeting held on 12 May 2026 were a correct record. | Decided | Open |
| 14 Jul 2026 | Verbal Update by Cabinet MembersRESOLVED that the verbal updates be noted. | Noted | Open |
| 14 Jul 2026 | Performance MonitoringRESOLVED that the report be noted. | Noted | Open |
| 14 Jul 2026 | 26/00042 - Proposed Expansion of Oakwood Park Grammar SchoolRESOLVED that the Committee considered and endorsed the proposed decision | Decided | Open |
| 14 Jul 2026 | 26/00043 - Expert at Hands (EaH) and Local Authority (LA) Special Education Needs & Disability (SEND) Transformation GrantRESOLVED that the Committee considered and endorsed the proposed decision | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.