23/00066: A28 Sturry Link Road - Compulsory Purchase Order

Approved Executive 5 papers

Growth, Environment & Transport Cabinet Committee approved this item on Wednesday 5 July 2023. Below is the council's own wording, with the papers it was decided on.

Item168

Resolved

RESOLVED to endorse the Cabinet Member on, the proposed decision to give approval to: i ) all acts required to acquire the land and rights for the carrying out and completion of the A28 Sturry Link Road scheme, including by means of a compulsory purchase order; ii) all acts required to provide new, or improved highways including the closure of private means of access for the carrying out and completion of the A28 Sturry Link Road scheme, including by means of a side roads order; iii) give delegation to the Corporate Director of Growth, Environment & Transport in consultation with the Cabinet Member for Highways and Transport to take relevant actions including but not limited to entering into contracts and other legal agreements, as necessary to implement the decision; and iv) confirm that other decisions in Record of Decision 18/00027 remain extant.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 6 pages

From: David Brazier – Cabinet Member for Environment & Transport

Simon Jones Corporate Director Growth, Environment & Transport

To: Environment & Transport Cabinet Committee – 5 July 2023

Decision No: 23/00066

Subject: A28 Sturry Link Road – Compulsory Purchase Order

Classification: Unrestricted

Past Pathway of Paper: None

Future Pathway of Paper: None

Electoral Division: Herne Village & Sturry, Canterbury North and Canterbury City North

Summary: Approval to use of compulsory purchase to secure the land and rights required for the scheme and to give programme certainty.

Recommendation(s):

The Cabinet Committee is asked to consider and endorse, or make recommendations to the Cabinet Member on, the proposed decision as follows and as indicated on the proposed decision sheet attached at Appendix D.

To give approval to:

i) all acts required to acquire the land and rights for the carrying out and completion of the A28 Sturry Link Road scheme, including by means of a compulsory purchase order

ii) all acts required to provide new, or improved highways including the closure of private means of access for the carrying out and completion of the A28 Sturry Link Road scheme, including by means of a side roads order; and

iii) give delegation to the Corporate Director of Growth, Environment & Transport in consultation with the Cabinet Member for Highways and Transport to take relevant actions including but not limited to entering into contracts and other legal agreements, as necessary to implement the decision and

iv) confirm that other decisions in Record of Decision 18/00027 remain extant. 1. Introduction

1.1The proposed A28 Sturry Link Road is a key element of new highway infrastructure that will link with development roads that together will support the consented development of 1,150 new homes at Sturry/Broad Oak. It will also indirectly support other consented strategic land allocations in Canterbury City Council’s Local Plan, at Sturry, at Herne, and along the Thanet Way.

1.2The scheme received planning consent in September 2021. See general arrangement plan at Appendix A.

1.3The main component of the scheme is a viaduct over two branches of the Great River Stour, and the Ashford to Ramsgate railway line.

1.4Tenders have been invited for a two-stage design and construction process. The preferred bidder has been notified and the contract is expected to be signed in late June 2023. There will be an initial commitment to the design phase and in particular the detailed design of the viaduct, to take advantage of the contractor’s experience, to achieve construction and cost efficiencies.

1.5The next critical stage is for land assembly. Negotiations have commenced and it is hoped that all land can be achieved by voluntary agreement. However, a compulsory purchase order needs to be progressed in parallel to ensure all land can be secured and to give programme certainty for a target start of construction during 2025. A compulsory purchase order is also a useful mechanism to gain title to any unknown or unregistered land, and to remove any restrictive covenants affecting use of the land.

1.6A new access is being provided to a residential property, and a potential development site, and a side roads order may also be required to formally close the existing accesses.

1.7At the outset of the project, a report to this Committee in May 2018, led to a range of decisions, in Record of Decision 18/00027, to enable the scheme to proceed. While this contained a specific reference to compulsory purchase, the use of compulsory purchase is a strong power available to a local authority and it is appropriate to seek an updated and explicit authority to publish and implement a compulsory purchase order.

2. The Land Required

2.1The proposed extent of land to be included in the compulsory purchase order is shown on the plan in Appendix B.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23/00066: A28 Sturry Link Road: Compulsory Purchase OrderReport 6 pages DownloadRead as text
PDF
Scheme PlanAppendix A 1 pages Download
PDF
Draft Compulsory Purchase Order PlanAppendix B 1 pages Download
PDF
Appendix CAppendix C 6 pages Download
PDF
PRODAppendix D 1 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 23/00066: A28 Sturry Link Road - Compulsory Purchase OrderThis decision
  2. 25/00110 - A28 Sturry Link RoadApproved
  3. Application CA/21/01854 (KCC/CA/0136/2021) - Construction of part of a new road (A28 Link Road) including viaduct between A28 Sturry Road and A291 Sturry Hill and associated on-line improvements at A28 Sturry Link Road, Sturry; KCC Major Capital Programme TeamDecided
  4. Application CA/19/00904 (KCC/CA/0091/2019) - Construction of part of a new road (A28 Link Road) including viaduct between A28 Sturry Road and A291 Sturry Hill and associated on-line improvements at A28 Sturry Link Road, Sturry; KCC Major Capital Programme TeamRefused
  5. A28/A291 Sturry Link Road, CanterburyDecided

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies