Kent County Council
Growth, Environment & Transport Cabinet Committee, Tuesday 13 January 2026 at 10.00am

25/00110 - A28 Sturry Link Road

Approved Executive 4 papers

AI summaryKent County Council's Growth, Environment and Transport Cabinet Committee considered a decision on the A28 Sturry Link Road, with Homes England weighing a grant of up to £24 million to close the funding gap.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPROD reviewed ahead of Cabinet Member decision
MoneyUp to £24 millionPossible Homes England grant figure
What happens nextMHCLG decision in 5 to 10 daysFunding approval expected late January 2026
Who it affectsSturry and Broad Oak residentsAlso Canterbury and East Kent communities

What was decided

The committee considered the proposed decision on the A28 Sturry Link Road, a key piece of infrastructure intended to cut congestion and support housing and economic growth in Canterbury and East Kent. Report P7

Officers confirmed the Homes England grant had passed to the Ministry of Housing, Communities and Local Government for formal approval, with a decision expected within five to ten days.

Officers clarified that Homes England had considered a grant value of up to £24 million, which would significantly offset the remaining funding gap and reduce the financial risk to the County Council.

Why

A funding gap remained after developer contributions and government grants, so the council is seeking support from the Brownfield Infrastructure and Land Bill Fund to allow the project to proceed without delay.

Delaying the project risks the planning permission expiring, which could lead to a costly resubmission of up to £4 million and reputational damage, as the scheme is vital to the Local Plan and traffic management. Report P10

Cancelling the project would mean £9 million of sunk costs, significant reputational harm, loss of future funding opportunities, and undermine housing growth plans while traffic continues to increase. Report P12

What happens next

Officers will work through the six planning conditions linked to environmental matters, particularly those affecting the River Stour, preparing and submitting the documentation needed to discharge them.

The Cabinet Member has asked officers to explore all options in case a funding shortfall arises, including the use of future Section 106 developer contributions.

Further legal advice will be sought before the council enters into the Grant Funding Agreement with Homes England, to ensure all conditions are acceptable and can be met. Report P3

The money

  • £9.8 million Homes England funding contribution referenced by Members
  • up to £24 million Homes England grant value under consideration
  • up to £4m Potential cost of resubmission if planning permission expires Report P10
  • £9m Sunk costs if the project is cancelled Report P12

Options considered

  • Rejected: Delay the project. Risks planning permission expiring, resubmission cost up to £4m, and reputational damage Report P10
  • Rejected: Delay without Homes England funding. Increases financial risk, leaves a funding gap, and requires KCC to advance Section 106 contributions not yet received Report P11
  • Rejected: Cancel the project. Would mean £9m of sunk costs, reputational harm, loss of future funding, and undermine housing growth plans Report P12

Implications

  • Legal: There are significant legal implications, and further legal advice will be taken before entering the Grant Funding Agreement with Homes England. Report P1, P2, P3
  • Equalities: The scheme brings long-term benefits for people in Age, Disability, Pregnancy and Maternity, and Carer Responsibility groups, with only minor short-term impacts during construction. Report P4
  • Financial: A Homes England grant of up to £24 million would significantly offset the funding gap and reduce the financial risk to the County Council.
  • Risk: Cancellation would result in £9m of sunk costs, reputational harm, and loss of future funding opportunities. Report P12
  • Other: Members raised environmental concerns about possible impacts on the River Stour from construction runoffs, and six planning conditions specifically address environmental matters.

Who and where

  • Residents of Sturry and Broad Oak, facing ongoing disruption from works around Sturry train station
  • Communities across Canterbury and East Kent, who would benefit from reduced congestion and new housing
  • People in Age, Disability, Pregnancy and Maternity, and Carer Responsibility groups, set to gain from improved access and connectivity Report P4

Timeline

  • Later in January 2026: Funding application decision expected from the Brownfield Infrastructure and Land Bill Fund
  • Within 5 to 10 days of the meeting: MHCLG expected to give a formal decision on the Homes England grant
  • 13 January 2026: Growth, Environment and Transport Cabinet Committee considered the proposed decision Report P7, P8

Plain English for the jargon

  • PROD: The council's decision record document, placed before a committee for consideration before a final decision is taken
  • MHCLG: Ministry of Housing, Communities and Local Government
  • Section 106: Planning obligations that require developers to contribute towards infrastructure or services
  • KCC: Kent County Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item58

Resolved

Decision to Members for consideration, aspects to be considered were: a) The A28 Sturry Link Road would be a critical piece of infrastructure required to reduce congestion and to support new housing and economic growth in Canterbury and East Kent. Although substantial funding had already been secured through developer contributions and government grants, a funding gap had remained. b) To address the funding gap, the County Council was seeking support from the Brownfield Infrastructure and Land Bill Fund. Securing funding would assist in mitigating the financial risk to the Council and ensured that the project could proceed without delay. A decision on the funding application was expected later in the month (January 2026). 2. In response to comments and questions from Members, the discussion covered the following: a) Members queried that the link road project being dependent on a £9.8 million funding contribution from Homes England and if funding was not secured, or if a shortfall arises, would County Council propose to address the deficit through future Section 106 developer contributions. The Cabinet Member suggested that a shortfall was unlikely but had instructed officers to explore all options. b) Officers updated that the grant had successfully passed the next stage of their approvals process. Officials from the Ministry of housing, Communities and Local Government (MHCLG) were present at that meeting. The proposal had now been passed to MHCLG for formal approval. Officers expected a decision within the next five to ten days, and the indications at the current stage remained positive. c) In Addition, officers responded to the £9.8 million funding gap that Members had referenced. Officers clarified that the figure did not represent the full value of the grant being requested. Homes England had applied their own contingency allowances, and their assessments did not include indexation when calculating the funding gap. d) KCC budgets had captured an anticipated level of indexation that would be expected to be met through developer contributions. As a result, Homes England had considered a grant value of up to £24 million, which would significantly offset the gap and reduce the overall financial risk to the County Council. e) Frustrations were shared on the lack of progress made with Network Rail in light of the works occurring around the Sturry train station location. Impacts to the local traffic were emphasised and included environmental concerns on the possibilities of the River Stour being impacted by building runoffs. Members asked for support in holding National Rail to account for the impacts that continued to disrupt the Sturry and Broad Oak areas. f) Officers highlighted the six planning conditions that related specifically to environmental matters, particularly those associated with the River Stour. Officers would be working through the process of preparing and submitting the necessary documentation to enable these conditions to be formally discharged. This included providing the evidence required to ... view the full minutes text for item 58.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Growth, Environment & Transport Cabinet Committee, 3 pages

There are significant legal implications associated with the scheme,

Legal oversight and advice has been engaged and provided throughout on all aspects the scheme to enable successful delivery. All risks will be considered and managed as part of the overall project management of the scheme.

Before entering into the Grant Funding Agreement with Homes England further legal advice will be sought to ensure all conditions are acceptable to KCC and can be met.

Equalities implications: The scheme brings long-term benefits for people in Age, Disability, Pregnancy & Maternity, and Carer Responsibility groups—improving access and connectivity. While there may be minor, short-term impacts during construction, no lasting negative effects are expected

Data Protection implications:

None Cabinet Committee recommendations and other consultation:

The proposed decision will be considered by the Growth, Environment and Cabinet Committee on 13 January 2026

This version of the PROD is included in the agenda pack for committee Members to review ahead of the meeting.

Any alternatives considered and rejected:

Delaying the project risks planning permission expiring, leading to costly resubmission (up to £4m) and reputational damage, as the scheme is vital for the Local Plan and traffic management.

Delaying without Homes England funding increases financial risk, leaving a funding gap and requiring KCC to advance S106 contributions not yet received.

Cancelling the project would result in £9m of sunk costs, significant reputational harm, loss of future funding opportunities, and undermine housing growth plans, while traffic would increase without capacity improvements. Any interest declared when the decision was taken and any dispensation granted by the Proper Officer:

…………………………………………….. ………………………………………………

Signed Date

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25-00110: Appendix A-PRODAppendix 3 pages DownloadRead as text
PDF
25-00110: Appendix B -Scheme PlanAppendix 1 pages Download
PDF
25-00110: Appendix C- EQIA: A28 Sturry Link RoadAppendix 6 pages Download
PDF
25/00110: A28 Sturry Link RoadDecisions 7 pages Download

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. 25/00110 - A28 Sturry Link RoadThis decision
  2. 23/00066: A28 Sturry Link Road - Compulsory Purchase OrderApproved
  3. Application CA/21/01854 (KCC/CA/0136/2021) - Construction of part of a new road (A28 Link Road) including viaduct between A28 Sturry Road and A291 Sturry Hill and associated on-line improvements at A28 Sturry Link Road, Sturry; KCC Major Capital Programme TeamDecided
  4. Application CA/19/00904 (KCC/CA/0091/2019) - Construction of part of a new road (A28 Link Road) including viaduct between A28 Sturry Road and A291 Sturry Hill and associated on-line improvements at A28 Sturry Link Road, Sturry; KCC Major Capital Programme TeamRefused
  5. A28/A291 Sturry Link Road, CanterburyDecided

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies