Resolved
RESOLVED to: a) Agree the proposed Internal Audit Plan for 2023/24 b) Note Priority 2 audits to be considered for the remainder of 2023/24 c) Approve the Internal Audit Charter d) Note the Key Performance Indicators for 2023/24
Governance and Audit Committee agreed this item on Thursday 6 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to: a) Agree the proposed Internal Audit Plan for 2023/24 b) Note Priority 2 audits to be considered for the remainder of 2023/24 c) Approve the Internal Audit Charter d) Note the Key Performance Indicators for 2023/24
APPENDIX A
Kent County Council Internal Audit Plan
July 2023 – May 2024
Governance and Audit Committee 6 July 2023 Section Navigation
Resources & Plan Summary
2023/24 AUDIT RESOURCES Cross Directorate
Adult Social Care & Health
CLIENTS DAYS Chief Executive Department (CED) Commercial Services Group, KFRS & 641 Childrens, Young People & Education TMBC (CYPE
Central Government Grants 50 Deputy Chief Executive Department (DCED) Interreg Grants 30 Growth, Environment & Transport (GET) KCC 1200 Appendix B - Priority 1 Parish Councils 50 Audits
TOTAL 1971 Appendix C - Priority 2 Audits Appendix D - Reasonable Assurance Model Appendix E - Audits against Corporate Risks Appendix F - Audit Charter Appendix G - Key Performance Indicators Section Navigation
Resources & Plan Summary
2023/24 AUDIT PLAN SUMMARY Cross Directorate
Adult Social Care & Health
Chief Executive Department (CED) DIRECTORATES Childrens, Young People & Education PRIORITIES CROSS ASCH CED CYPE DCED GET TOTALS (CYPE DIRECTORATE Deputy Chief Executive Department (DCED)
Growth, Environment PRIORITY 1 6 7 9 4 6 7 39 & Transport (GET)
PRIORITY 2 0 6 10 3 11 4 34 Appendix B - Priority 1 Audits TOTALS 6 13 19 7 17 11 73 Appendix C - Priority 2 Audits Appendix D - Reasonable Assurance Model Appendix E - Audits against Corporate Risks Appendix F - Audit Charter Appendix G - Key Performance Indicators Section Navigation 2. Risk Based Audits Resources & Plan 2.1 Cross Directorate Summary
Audit Title Nature of Work Scope Cross Directorate
Gifts & Hospitality Assurance Priority 1 Adult Social Care & Health Enterprise Business Capabilities (Oracle) Consultancy Priority 1 Annual Governance Statement Assurance Priority 1 Chief Executive Department (CED) Project Management Assurance Priority 1 Childrens, Young Contract Management Assurance Priority 1 People & Education (CYPE Home to School Transport Follow Up Assurance Priority 1 Deputy Chief Executive Department (DCED)
Growth, Environment & Transport (GET)
Appendix B - Priority 1 Audits
Appendix C - Priority 2 Audits Appendix D - Reasonable Assurance Model Appendix E - Audits against Corporate Risks Appendix F - Audit Charter Appendix G - Key Performance Indicators Section Navigation 2. Risk Based Audits Resources & Plan 2.2 Adult Social Care & Health (ASCH) Summary
Audit Title Nature of Work Priority Cross Directorate
Usage of Factoring Companies Assurance Priority 1 Adult Social Care & Joint Funding & Governance (NHS) Assurance Priority 1 Health NHS Joint Working & Pooled Budgets Chief Executive Safeguarding (ASCH) Assurance Priority 1 Department (CED) Public Health Assurance Mapping Assurance Priority 1 Childrens, Young People & Education Individual Contracts to Care Providers Follow Up Assurance Priority 1 (CYPE Direct Payments / Abuse of Kent Cards Assurance Priority 1 Deputy Chief Executive Department (DCED) Hospital Discharge Assurance Priority 1 Payment to Providers Assurance Priority 2 Growth, Environment & Transport (GET) Section 117 Aftercare Payments Assurance Priority 2 Appendix B - Priority 1 Shared Lives Assurance Priority 2 Audits ASCH Programme Management / Commissioning Assurance Priority 2 Appendix C - Priority 2 Public Health External Funding Review (Assurance Mapping) Assurance Priority 2 Audits Health Visitor Service (Backlog) Performance and Recruitment & Retention of Staff Assurance Priority 2 Appendix D - Reasonable Assurance Model Appendix E - Audits against Corporate Risks Appendix F - Audit Charter Appendix G - Key Performance Indicators Section Navigation 2. Risk Based Audits Resources & Plan 2.3 Chief Executive Department (CED) Summary
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan 2023-24Report | 24 pages | DownloadRead as text |
PDF |
Rolling Internal Audit Plan 23-24Report | 5 pages | Download |
Follow Governance and Audit Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Oct 2026 | Minutes of the meeting held on 23 July 2026RESOLVED that the minutes be signed by the Chair as a correct record of the meeting held on 23 July 2026. | Decided | Open |
| 15 Oct 2026 | Draft Statement of AccountsRESOLVED that the Committee: a. NOTE the Kent County Council Auditor’s Interim Annual Report 2025–26; b. NOTE the Aud... | Noted | Open |
| 15 Oct 2026 | Letters of Representation - Kent County Council and Kent Pension FundRESOLVED that the Committee approve the Letters of Representation for Kent County Council and the Kent Pension Fund, ... | Approved | Open |
| 23 Jul 2026 | Minutes of the meeting held on 19 May 2026RESOLVED that the minutes of the meeting held on the 19 May 2026 were a true and accurate record and a paper copy sho... | Decided | Open |
| 23 Jul 2026 | Verbal Update on Committee BusinessIt was agreed that a draft version of the tracker format would be shared with Members at the next meeting to provide ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.