Resolved
RESOLVED to note that there are no changes recommended to the accounting policies and to note the provisional audit timetable.
Governance and Audit Committee noted this item on Thursday 6 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note that there are no changes recommended to the accounting policies and to note the provisional audit timetable.
By: Peter Oakford - Deputy Leader and Cabinet Member for Finance, Corporate and Traded Services Zena Cooke – Corporate Director Finance
To: Governance and Audit Committee – 6 July 2023
Subject: Revised Accounting policies and provisional audit timetable
Classification: Unrestricted _____________________________________________________________
Summary: This report asks Members to note that there are no changes to accounting policies and to note the provisional external audit timetable.
FOR INFORMATION _____________________________________________________________
Accounting policies
1. The CIPFA Code of Practice requires authorities to follow International Accounting Standard 8 (IAS 8) - Accounting Policies, Changes in Accounting Estimates and Errors. Accounting policies are defined as “… the specific principles, bases, conventions, rules and practices applied by an entity in preparing and presenting financial statements.”
2. For 2022-23 there are no changes to the accounting policies to report.
Draft accounts and provisional external audit timetable
3. The Accounts and Audit Regulations 2015 requires that draft accounts be available for public inspection for a single period of 30 working days and includes the first 10 working days of June.
The 18th May Committee was informed that the 2022-23 Statement of Accounts would not be published until the 1 st July and available for public inspection period for a single period of 30 days and includes the first 10 working days of July.
We are required to publish a notice stating that the inspection period has not commenced, the reason why and to inform when it will be reasonably be practicable to do so. This was published on the 22nd May 2023.
3.2Paragraphs 3.3 to 3.6 set out the background behind the delays in completion of the audit and sign off of the accounts, which are the contributing factors in delaying the publication of the draft 2022-23 Statement of Accounts.
3.3The audit of the 2021-22 accounts was completed on the 31 st March 2023 and this impacted on the commencement of the 2022-23 accounts. 3.4 Prior to the COVID-19 pandemic our draft accounts have been published as required on 31st May and have met the inspection period.
For financial years 2019/20, 2020/21 and 2021/22, the Accounts and Audit Regulations were amended to give extra time for local authorities and auditors. We were required to publish draft accounts by no later than the 1 st August. Our draft accounts were published as follows:
The 2019/20 accounts on 30 June 2020. With the inspection period commencing on the 1st July 2020, The 2020/21 accounts on 30 June 2021. With the inspection period commencing on the 1st July 2021, and The 2021/22 accounts on 1 August 2022. With the inspection period commencing on the 1st August 2022.
3.5The audit and sign off of the accounts up until 2019/20 has been completed by 31st July.
Over the last three years we have seen an extended audit timetable and delays in the signing off of the accounts. Detailed below are the sign off dates for years 2019/20 and 2020/21:
The 2019/20 accounts were signed off on 27th November 2020. This met the deadline as set out in the Accounts and Audit Regulations, amended for the pandemic. The 2020/21 accounts were signed off on 13th December 2021. This was after the deadline of 30th November 2021.
3.6The Accounts and Audit Regulations for the 2021/22 accounts were amended and required the publication for final, audited accounts to be the 30th September 2022. The expectation, as advised by our auditors, was that the 2021/22 audit of the accounts would have completed by the end of November/beginning of December 2022. The accounts were eventually signed off on the 31st March 2023. The following issues led to the delay in sign off:
1. Infrastructure Assets
Waiting for the statutory instrument to be approved to confirm the disclosure requirements. Confirmation was made in January 2023.
2. Completion of the following items:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revised Accounting PoliciesReport | 3 pages | DownloadRead as text |
Follow Governance and Audit Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Oct 2026 | Minutes of the meeting held on 23 July 2026RESOLVED that the minutes be signed by the Chair as a correct record of the meeting held on 23 July 2026. | Decided | Open |
| 15 Oct 2026 | Draft Statement of AccountsRESOLVED that the Committee: a. NOTE the Kent County Council Auditor’s Interim Annual Report 2025–26; b. NOTE the Aud... | Noted | Open |
| 15 Oct 2026 | Letters of Representation - Kent County Council and Kent Pension FundRESOLVED that the Committee approve the Letters of Representation for Kent County Council and the Kent Pension Fund, ... | Approved | Open |
| 23 Jul 2026 | Minutes of the meeting held on 19 May 2026RESOLVED that the minutes of the meeting held on the 19 May 2026 were a true and accurate record and a paper copy sho... | Decided | Open |
| 23 Jul 2026 | Verbal Update on Committee BusinessIt was agreed that a draft version of the tracker format would be shared with Members at the next meeting to provide ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.