Resolved
RESOLVED to agree the recommendations as outlined in the report.
Growth, Environment & Transport Cabinet Committee agreed this item on Thursday 11 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to agree the recommendations as outlined in the report.
From: Neil Baker Cabinet Member, Highways and Transportation
Simon Jones – Corporate Director, Growth Environment and Transport.
To: Environment & Transport Cabinet Committee Meeting – 11th January 2024.
Subject: Highways Term Maintenance Contract – Update and Next Steps
Key decision – No
Classification: Unrestricted
Past Pathway of Paper: N/A
Future Pathway of Paper: N/A
Electoral Division: All
Summary: The current and recently awarded Highways Term Maintenance Contract with Amey Highways commenced on 1st September 2023 for a period of 32 months.
This contract will end on 30th April 2026 by which time a new commissioned contract will need to be procured and put in place. This ensures continuity of a Highways Maintenance Service and that KCC can meet its statutory responsibilities as Highway Authority in accordance with the Highways Act 1980 and other pertinent mandatory legislation.
There are several key lessons learnt from this process including the need to ensure timely reporting of key issues and progress to this committee.
However there has been unprecedented disruption and volatility in the markets that has caused a delay in the commissioning cycle. Global economic factors and double-digit inflation would have seriously impacted a contract of this size, value, complexity, and duration.
This in turn could have placed greater operational risk with a potentially unaffordable contract for KCC to deliver its statutory highways service.
It was anticipated that by extending the prevailing contract by 32 months would provide a period undertake a full commissioning process and to allow the highways market to stabilise.
Recommendation(s): Environment and Transport Cabinet Committee members are asked to endorse or to make comment or recommendation to the Cabinet Member in relation to the report, lessons learnt and next steps. 1. Introduction. 1.1 On 21 August the Cabinet Member for Highways and Transport took a decision to:
Award a new contract to Amey Highways for 32 months. Delegate to the Corporate Director of Growth, Environment and Transport in consultation with the Cabinet Member for Highways and Transport to take relevant actions including but not limited to entering into contracts and other legal agreements, as necessary to implement the decision. Agree to the proposed procurement timeline for the replacement contract.
2. Reason(s) for decision: 2.1 KCC has a legal duty to maintain its respective sections of the highway network under section 41 of the Highways Act 1980 and this demands continuity of operational service. 2.2 Many of these services are delivered through a Highway Term Maintenance Contract (HTMC) with Amey Highways Ltd. The previous contract expired on 31 August 2023. A new contract was urgently needed to be in place from 1 September 2023. 2.3 Several key services are delivered through this contract including:
Winter Service Provision – i.e. gritting/salting of the road network during freezing conditions including ploughing during snow events. Drainage Maintenance and Capital Projects – i.e. cyclical highway drainage cleansing, emergency response during storm events and capital drainage repair schemes. Structures – i.e. bridge repairs, tunnels maintenance and management and construction of new structures. Highway patching and small- to medium-scale road asset renewal works – i.e. pothole repairs and larger surface defect repairs of the highway Pavement asset preservation services – i.e. carriageway and footway life extension treatments such as surface dressing. Emergency Response – i.e. respond to emergencies across the network due to weather, emergency services support, vehicle collisions and structural asset failure both in hours and out of hours, 24/7/365. Highway Improvement Scheme Delivery – i.e. construction of schemes for crash remedial measures, engineering and traffic schemes and s106 requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Term Maintenance Contract: Update and Next StepsReport | 7 pages | DownloadRead as text |
Follow Growth, Environment & Transport Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... | Decided | Open |
| 5 May 2026 | Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... | Decided | Open |
| 5 May 2026 | Winter Service UpdateRESOLVED to note the Winter Service Update . | Noted | Open |
| 5 May 2026 | Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. | Noted | Open |
| 5 May 2026 | 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.