Highways and Transportation Enterprise Term Maintenance Contract
NotedScrutiny1 paper
Environment, Highways and Waste Policy Overview and Scrutiny Committee noted this item on Thursday 12 January 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the following be noted:- (a) the implementation of the Term Maintenance Contract had resulted in some promising early results; (b) further operational improvements and staff development were required to extract full efficient working; and (c) IT System enhancements across both organisations were identified and were planned to be delivered.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Environment, Highways and Waste Policy Overview and Scrutiny Committee, 3 pages
To: Environment Highways & Waste Policy Overview & Scrutiny Committee - 12 January 2012
By: Bryan Sweetland, Cabinet Member for Environment Highways and Waste
John Burr, Director, Highways and Transportation
Subject: Highways and Transportation Enterprise Term Maintenance Contract
Classification: Unrestricted
Summary: This report details an assessment and impact of the Highways and Transportation term maintenance contract delivered by Enterprise since 1st September 2011.
1. Introduction
On the 1st September 2011, Highways and Transportation commenced a new Term Maintenance Contract with Enterprise AOL. This is to provide core maintenance services, these include; • Routine maintenance, carriageway, footway structure repairs • Winter Service • Emergency out of hour’s response • Drainage gulley emptying and repairs • Signs and lines maintenance • Integrated transport schemes • Street lighting • Scheme delivery • Tunnels and Structure
The initial contract term is five years; this could be extended by a further five years but is subject to satisfactory performance and assessment by the County Council.
2. Progress
Enterprise have invested heavily in this contract, they have mobilised a fleet of 198 vehicles this includes the 63 gritting vehicles.
The headcount establishment of those working on the contract is 321 staff, of these 309 were TUPE transferred from Ringway. They have appointed an entirely new management team. They have also appointed 79 approved sub contractors who are available to work on the contract.
In the first three months of operation 19,836 orders (£5.2m) have been completed, 2,100 salt bins filled and 4,000t out of the 23,000t salt stock has been used and replenished.
Kent has invested heavily in training (2,648 hours), this is vital to ensure that officers understand the contract, comply with its requirements and ensure that best value is achieved. This will continue for the next few months – training has so far centred around ordering work in accordance with the contract and using the price list in accordance with the engineering specifications.
3. Delivery of service
Enterprise and Kent have worked well during the start of the contract; it is notable that both organisations have commented that there has been a common approach to operate a successful contract that delivers work to high quality, efficiently and to the appropriate price.
Kent’s approach has been to be firm but fair in all commercial/contractual matters, the principles of the price list are robustly adhered to where new rates or pricing queries have been resolved. Further to this, depot and property lease contracts and charges have been fully applied and penalties have been applied where there has been non compliance of the Kent Permit Scheme.
Routine enquiries reported by the public completed in 28 days are just above standard at 91%.
At each payment application managers have scrutinised cost and payment disputes have been made – this is a healthy process and quite normal in such contracts.
4. Issues and further developments
The contract handover has been almost seamless with only a slight drop in output experienced. Two service areas that were affected are street lighting maintenance and MHF schemes. Both these areas have been subject to increased focus to resolve the delays and actions have been taken to ensure that full programmed delivery can be assured and output increased.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Highways and Waste Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
Financial Monitoring Report 2011/2012RESOLVED that the budget variations for the EHW Portfolio for 2011/12 based on the January full monitoring report to ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.