From: Derek Murphy, Cabinet Member for Economic Development
Simon Jones, Corporate Director Growth, Environment and Transport
To: Growth, Economic Development and Communities Cabinet Committee - 18 January 2024
Subject: 2023 Community Infrastructure Levy Position
Classification: Unrestricted
Past Pathway of report: N/A
Future Pathway of report: N/A
Electoral Division: County Wide
Summary: This report is designed to provide a background understanding of the Community Infrastructure Levy (CIL) and the emerging pattern of reduced developer contribution funding secured through this mechanism yet required to mitigate the impacts of growth on County Council infrastructure and services in certain locations.
Recommendation: The Committee is asked to note the contents of the report and make any recommendations to the Cabinet Member.
1. Introduction
1.1The Community Infrastructure Levy (CIL) is a planning charge, introduced by the Planning Act 2008, as a tool for local planning authorities in England and Wales to help deliver infrastructure to support the development of their area. It came into force on 6 April 2010 through the Community Infrastructure Levy Regulations 2010. Changes were subsequently made to the Community Infrastructure Levy Regulations through the Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 which came into force on 1 September 2019.
1.2Development may be liable for a charge under CIL depending on rates and criteria that the local planning authority i.e. a district, borough or city council has calculated and set in its area.
1.3New developments that create net additional 'gross internal area' of 100 square metres or more, or create new dwellings, are potentially liable for the levy. The levy is a financial tariff paid at a cost per sq. metre of development. There are however a number of exemptions and reliefs that alleviate or reduce the charges on certain development types or in particular geographical areas.
1.4Each year all district, borough and county councils are required to produce their Infrastructure Funding Statements (IFS). Authorities should consider the known and expected infrastructure costs taking into account other possible sources of funding to meet them. This process should help the local planning authority to identify the infrastructure funding gap and a levy funding target.
1.5This paper should be read in conjunction with the January 2024 GEDCCC 2023 Infrastructure Funding Statement paper.
2. The Five CIL Authorities in Kent
2.1Developer contributions are secured through the CIL mechanism within five Local Planning Authorities in the county: Canterbury; Dartford; Folkestone and Hythe; Maidstone; and Sevenoaks. In these areas the contributions are collected by the Local Planning Authorities. In the last financial year, of the five CIL authorities, the County Council only received and spent contributions in Folkestone and Hythe.
2.2Folkestone and Hythe are the only CIL authority that routinely provides KCC with a proportion (35%) of its CIL income, whereas other authorities invite KCC to submit bids to be made towards projects, then determining their success through their own unique internal governance processes. The bidding process required in some areas is particularly resource intensive and due to their competitive nature can often lead to failure and abortive work. Bids are open to all infrastructure providers that can include the County Council, community groups, departments within their own authority or utility providers.
2.3Taking into context that any of KCC’s bids would be to support strategic infrastructure already identified as being necessary through the local plan or planning application processes, the bidding processes is not conducive to securing funding for essential high value statutory infrastructure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2023 Community Infrastructure Levy PositionReport | 8 pages | DownloadRead as text |
Follow Growth, Economic Development and Communities Cabinet Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Nov 2025 | Election of ChairRESOLVED that [name removed] be elected as Chair of the Growth, Economic Development and Communities Cabinet Committee. | Decided | Open |
| 11 Nov 2025 | Minutes of the meeting held on 11 September 2025RESOLVED that the minutes of the meeting held of 11 September 2025 were a correct record and they be signed by the Ch... | Decided | Open |
| 11 Nov 2025 | KMEF- Ambition 2- Widen opportunities and unlock talentRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Regional Energy Strategic PlanRESOLVED to note the report. | Noted | Open |
| 11 Nov 2025 | Decisions taken between Cabinet Committee Meetings- 25/00084It was agreed that consideration would be given to Member involvement in the reinstated Visitor Economy and Inward In... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.