Growth, Environment & Transport Cabinet Committee, Tuesday 13 January 2026 at 10.00am

Gravesend - Tilbury Ferry Petition Update

Noted Executive 1 paper

AI summaryKent's Growth, Environment and Transport Cabinet Committee noted an update on the Gravesend to Tilbury ferry, which ceased in March 2024 after Thurrock withdrew its 50% funding share.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decision taken to reintroduce the ferry
MoneyNo new moneyNo budget currently assigned to the service
What happens nextWorking group continuesThames Estuary Growth Board leads ongoing study
Who it affectsThames-side passengers and councilsGravesend, Tilbury, Kent and Thurrock users

What was decided

The committee noted the report on the Gravesend to Tilbury ferry petition, taking no new decision on the service. Report 8.1

The position recorded is that reinstatement is not a decision for Kent County Council alone and that Kent cannot bear the full subsidy. Report 2.11, 3.2

Why

The ferry is a non statutory service, so Kent County Council cannot be expected to fund it in full. Report 2.9, 7.3

Thurrock Council withdrew its share of the subsidy during contract extension talks, leaving Kent to fund the final months alone. Report 2.7, 2.8, 7.2

No Kent County Council budget is currently set aside for the service and any contribution would need new funding. Report 3.2, 4.3

What happens next

Officers will continue working with the Thames Estuary Growth Board and other stakeholders on future funding options. Report 2.11, 7.4, 8.1

If the service is reintroduced with Kent support, communication and consultation would be required. Report 6.1

The money

  • £440k Forecast cost of providing the ferry at the point of cessation Report 2.5
  • £230k Expected to be met by passenger fares in the final year Report 2.5
  • £210k Subsidy requirement at the point of cessation Report 2.5

Options considered

  • Rejected: Kent County Council bears the full subsidy to reintroduce the ferry on its own. Non statutory service, no budget assigned, and cannot be a Kent only decision Report 2.9, 2.11, 3.2, 7.3

Implications

  • Financial: No current Kent budget is assigned to the ferry; any contribution would require additional funding. Report 3.2, 4.1, 4.3
  • Legal: No legal implications for Kent County Council arising from this activity. Report 5.1
  • Other: If reintroduced with Kent support, communication and consultation would be needed. Report 6.1
  • Risk: Costs to reinstate are unknown and, given inflation, would likely exceed the previous £210k subsidy. Report 4.1

Who and where

  • Kent County Council as contract holder and former co funder Report 2.3, 2.8, 7.1
  • Thurrock Council, which withdrew its funding share Report 2.7, 7.2
  • Gravesham Council, Port of London Authority, Port of Tilbury and prospective operators on the working group Report 2.11
  • Passengers who used the Gravesend to Tilbury crossing for work, education and shopping Report 2.4, 2.5

Timeline

  • Until 2000: Service ran without public subsidy Report 2.1
  • From 2000: Service required subsidy shared 50/50 between Kent and Thurrock Report 2.2, 2.3
  • In the last full year of operation: 113,000 journeys were made Report 2.5
  • October 2023: Previous contract due to expire; short term extension negotiated Report 2.6
  • October 2023 to March 2024: Kent met the full cost alone after Thurrock withdrew Report 2.8
  • March 2024: Contract expired following consultation and equalities impact assessment Report 2.9
  • 2026-01-13: Committee noted the petition update report

Plain English for the jargon

  • Non statutory service: A service the council is not legally required to provide
  • Thames Estuary Growth Board: Body leading the study on future funding options for the ferry
  • Equalities Impact Assessment: Assessment of the impact of a decision on people with protected characteristics
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

RESOLVED to note the Report
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

Papers for this item

Kept in our archive, download once signed in
PDF
Gravesend: Tilbury Ferry Petition UpdateReport 4 pages Withheld: personal details

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. Gravesend - Tilbury Ferry Petition UpdateThis decision
  2. Tilbury-Gravesend Ferry UpdateNoted
  3. Update on the Future of the Gravesend to Tilbury Ferry ServiceNoted

More from Kent Growth, Environment & Transport Cabinet Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of the meeting held on 05/05/2026RESOLVED that the minutes of the meeting held 5 May 2026 were a correct record and that a paper copy be signed by the... Decided Open
5 May 2026 Minutes of the meeting held on 10.03.2026RESOLVED that the minutes of the meeting held 10 March 2026 were a correct record and that a paper copy be signed by ... Decided Open
5 May 2026 Winter Service UpdateRESOLVED to note the Winter Service Update . Noted Open
5 May 2026 Tilbury-Gravesend Ferry UpdateRESOLVED to note the Gravesend to Tilbury Ferry Update. Noted Open
5 May 2026 26/00018 - Prioritisation of Definitive Map Modification ApplicationsRESOLVED to endorse the proposed decision, namely: a) APPROVE the changes to the Statement of Priorities for Definiti... Approved Open