RESOLVED :1) That the outturn of the capital programme for 2014/2015 of £11,040,092 be noted. 2) That the financing arrangements for the 2014/2015 capital programme be approved. 3) That the revised 2015/2018 capital programme as detailed in the report be approved.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1) that Cabinet note the outturn of the capital programme for 2014/2015 of £11,040,092.
2) that the financing arrangements for the 2014/2015 capital programme be approved.
3) that Cabinet approve the revised 2015/2018 capital programme as detailed in the report. Reason for Decision To report the outturn 2014/2015 for the Capital Programme and update members on capital spending and resources for 2015-2018. 1 Introduction
1.1This report presents the outturn of the 2014/2015 capital programme and provides details of amendments and rephasing resulting from under and overspends and their impact on the 2015/2018 programme. The report also outlines the financing of the 2014/2015 programme.
2 Capital Programme 2014/2015
2.1The full capital programme for 2014/2015 is shown at Appendix 1 and provides details of the outturn for individual schemes, together with amendments and rephasing to/from future years.
2.2A full updated Capital Programme 2014/2015 of £13,715,050 was reported at the Cabinet meeting on 3 February 2015 and approved by Council on 26 February 2015.
2.3The final figures for the outturn on the capital programme show that it will be necessary to carry forward a further £3,233,350 as schemes carry over to future years. In a number of cases there were over or under spends which net to a £530,952 overspend across the overall capital programme.
The main schemes where over/(underspends) are reported are detailed in the table below. The small net overspend will be funded from overall capital resources.
£ Saturday Market Place refurbishment – final scheme costs 43,024 Tuesday Market Place refurbishment - final invoice less than (5,247) provided for at previous year end Queen Elizabeth Hospital Roundabout Road Widening - final (10,567) invoice less than provided for at previous year end Princess Theatre – third party contribution and lower scheme (14,689) cost ICT – Underspend across a number of ICT projects (12,884) Miscellaneous movements 1,880 1,517 In addition there are a number of schemes which come with resources ie reserves where the capital programme was not updated and amended to fully reflect the actual costs. The main schemes are detailed in the table below. The apparent overspend is met from earmarked reserves/grants unapplied/unsupported borrowing and there is no impact on the bottom line funding of the capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.