The Committee supported the recommendations to Cabinet as follows: 1) That Cabinet note the outturn of the Capital Programme for 2015/2016 of £13,924,624. 2) That the financing arrangements for the 2015/2016 Capital Programme be noted. 3) That Cabinet approve the revised 2016/2020 Capital Programme and financing as detailed in the report. ... view the full minutes text for item AR10
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
1) that Cabinet note the outturn of the capital programme for 2015/2016 of £13,924,624.
2) that the financing arrangements for the 2015/2016 capital programme be noted.
3) that Cabinet approve the revised 2016/2020 capital programme and financing as detailed in the report. Reason for Decision To report the outturn 2015/2016 for the Capital Programme and update members on capital spending and resources for 2016-2020. 1 Introduction
1.1This report presents the outturn of the 2015/2016 capital programme and provides details of amendments and rephasing resulting from under and overspends and their impact on the 2016/2020 programme. The report also outlines the financing of the 2015/2016 programme.
2 Capital Programme 2015/2016
2.1The full capital programme for 2015/2016 is shown at Appendix 1 and provides details of the outturn for individual schemes, together with amendments and rephasing to/from future years.
2.2A full updated Capital Programme 2015/2016 of £15,746,950 was reported at the Cabinet meeting on 2 February 2016 and approved by Council on 25 February 2016.
2.3The final figures for the outturn on the capital programme show that it will be necessary to carry forward a further £1,998,850 as schemes carry over to future years. In a number of cases there were over or over spends which net to a £20,352 underspend across the overall capital programme.
The main schemes where over/(underspends) are reported are detailed in the table below.
£ Enterprise Centre – Ground Works (24,483) Sports Pavilion Kingsway Replacement - final retention 23,284 payments Joint Venture / Housing Developments – Set Up Funding (10,310) (correction of prior year expenditure) Private Sector Housing – Small Grants (44,423) Community Projects - Financial Assistance (11,486) North Lynn Industrial Estate - 1-8 Brygen Road reroofing 27,899 Miscellaneous movements 19,167 (20,352) In addition there are a number of schemes which come with resources ie reserves where the capital programme was not updated and amended to fully reflect the actual costs. The main schemes are detailed in the table below. The apparent overspend is met from earmarked reserves/grants unapplied/unsupported borrowing and there is no impact on the bottom line funding of the capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.