RECOMMENDED : 1) That the amendments to capital schemes and resources for the 2018-2023 capital programme as detailed in the report be approved. 2) That new capital bids be funded from available capital resources and included in the capital programme 2019-2023 as detailed in the report. Reason for Decision To report amendments, re-phasing and resources to the 2018-2023 Capital Programme
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Partly Exempt Would any decisions proposed : Any Mandatory especially (a) Be entirely within Cabinet’s powers to decide NO affected (b) Need to be recommendations to Council YES Wards None (c) Be partly for recommendations to Council NO and partly within Cabinets powers – Lead Member: Councillor Brian Other Cabinet Members consulted: Long Other Members consulted: E-mail:cllr.brian.long@west- norfolk.gov.uk Lead Officer: Lorraine Gore Other Officers consulted: Management Team, E-mail: lorraine.gore@west- Service Managers norfolk.gov.uk Direct Dial: Financial Policy/Personnel Statutory Equal Risk Implications Implications Implications Opportunities Management YES YES (incl S.17) Implications Implications NO NO YES If not for publication, the paragraph of Schedule 12A of the 1972 Local Government Act considered to justify that is paragraph 3
Date of meeting: 5 February 2019
CAPITAL PROGRAMME AND RESOURCES 2018-2023
Summary This report:
revises the 2018/2019 projections for spending on the capital programme sets out an estimate of capital resources that will be available for 2018-2023 details new capital bids that are recommended to be included in the capital programme for the period 2019-2023 outlines provisional figures for capital expenditure for the period 2018-2023 Exempt section details proposed future corporate capital projects
Recommendations It is recommended that:
1) Cabinet recommends to Council the amendments to capital schemes and resources for the 2018-2023 capital programme as detailed in the report. 2) Cabinet recommends to Council that new capital bids are to be funded from available capital resources and included in the capital programme 2019-2023 as detailed in the report.
Reason for Decision To report amendments, rephasing and resources to the 2018-2023 Capital Programme 1. Introduction
1.1This report presents the capital programme for the period 2018 to 2023. The capital programme forms part of the Council’s longer term Financial Plan, and is updated as part of the overall budget and council tax setting process.
1.2The current economic conditions continue to create a challenging environment for achieving capital receipts to support the funding of the Council’s capital programme. The interest in new homes delivered through the Council’s housing developments continues to be strong, with homes being sold off of plan. At the same time the Council aims to deliver a number of major projects within limited resources. The Council has considered the impact of market prices as the scheme progresses and the possibility that the housing market may slow and to mitigate this risk has established West Norfolk Property Limited (Cabinet 8 January 2018) for Private Rental Properties.
1.3The Council is faced with a situation where capital resources to fund the capital programme continue to be limited. There are competing demands for use of these resources, including investment in projects which will deliver revenue savings.
1.4This report sets out a programme for 2018-2023 that can be delivered if predicted land sales come about. Certain capital funds come from grants and use of reserves but a large part of funds are to come from land sales. The sums included in 2018-2023 are anticipated receipts from identified sites, phase 2 (final 2 show homes) and phase 3 of the Housing Joint Venture on the NORA site and the Major Housing Development.
1.5The capital programme 2018-2023 includes a number of major housing projects, summarised in the table below. The delivery of new homes through this project provides essential funding to support the revenue budget, both through new homes bonus and increases to the council tax base.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.