PUBLIC SECTOR DE-CARBONISATION SCHEME

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.

ItemCAB243

Resolved

RESOLVED : 1) That a s the value of the required separate contract is above £500,000 for these extra grant funded works, the utilisation of our existing Re:Fit delivery partners, Ameresco , to deliver the project on behalf of the council be approved. 2) That the utilisation of the grant awarded under the Public Sector Decarbonisation Scheme, subject to the granting of any specific consents required for any of the buildings be noted and endorsed. Reason for Decision To ensure the delivery of the project within the relatively stringent timescales set out by the terms of the grant from the Department of Business, Energy & Industrial Strategy (BEIS).
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Summary

The purpose of this report is to update Cabinet on grants the council has been awarded, from the Department of Business, Energy & Industrial Strategy (BEIS), and to seek approval to enter into a contract to undertake the project to utilise those grants. The grants received are from the Government’s £1 billion Public Sector Decarbonisation Scheme (PSDS) fund, and are for the provision of non/low carbon generating technologies, such as solar PV and air and ground source heat pumps, within several council owned buildings. It is a continuation of the council’s programme of decarbonising its estate, which is taking place through the Re:Fit programme.

Two bids were submitted in two separate bidding rounds, with the first round bid for £2,838,546 approved by BEIS in January. On 22 February, the council also received confirmation that the second round bid has also been approved, subject to conditions, which is for a further £1,013,138. The total grants that have been received from the PSDS fund is therefore £3,851,684.

In addition, as this is a continuation of the Re:Fit programme the council is undertaking, the council will utilise the existing agreement with our Re:Fit partners, Ameresco, plus a new JCT Design & Build contract, to complete the project. As the value of the works is over £500,000, albeit this is 100% grant funded, further Cabinet approval is sought.

Recommendation

1) As the value of the required separate contract is above £500,000 for these extra grant funded works, that Cabinet approve the utilisation of our existing Re:Fit delivery partners, Ameresco, to deliver the project on behalf of the council.

1 2) That Cabinet notes and endorses the utilisation of the grant awarded under the Public Sector Decarbonisation Scheme, subject to the granting of any specific consents required for any of the buildings.

Reason for decision

To ensure the delivery of the project within the relatively stringent timescales set out by the terms of the grant from the Department of Business, Energy & Industrial Strategy (BEIS).

Background

1.1Members will be aware of the council’s Re:Fit programme, as it seeks to reduce carbon emissions from its estate. The Re:Fit programme has involved works including the provision of solar photovoltaics, and building fabric improvements such as extra insulation. Late last year, an opportunity arose for the council to submit two bids to the Government’s £1 billion Public Sector Decarbonisation Scheme (PSDS) fund, for technologies and works to further support the decarbonisation of the council’s public buildings. One bid was submitted at the end of November 2020, and the other on the 11th January 2021. Each bid included several council buildings. The choice of buildings was based on those considered to be appropriate, but there were also timescale constraints in assessing particular buildings, for what was a very technical bid, even at this High Level Assessment (HLA) stage. In essence those buildings we were able to technically assess first, within the tight timescales available, were submitted as part of the first bid. The remaining buildings formed part of the second bid.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PUBLIC SECTOR DE-CARBONISATION SCHEMEReport 315 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
AB
Alexa BakerOfficer, expected
KB
Kate BlakemoreOfficer, expected
RB
Councillor Richard BluntCommittee Member, present
JC
Jemma CurtisCouncil Staff, expected
SD
Councillor Stuart DarkCommittee Member, apologies
MD
Michelle DreweryOfficer, expected
ED
Emma DuncanOfficer, expected
DG
Debbie GatesOfficer, expected
PG
Councillor Peter GidneyCommittee Member, present
LG
Lorraine GoreOfficer, expected
GH
Geoff HallOfficer, expected
AI
Aaron IrelandCouncil Staff, expected

All 18 on the meeting page

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open