RECOMMENDED: That the Council enters a contract with Lovell Partnerships Ltd under the Major Housing Contract to deliver this project, subject to planning permission being granted. Reason for Decision 1) To develop this site using the Major Housing contract with Lovell Partnerships Limited. 2) To allow the scheme to be developed using traditional methods. 3) To include the tenure mix shown in section 2.4 of this report.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Statement in response to Parking Loss at Southend Road – Hunstanton Prepared by: James Grant Property Services
January 2021 2
1. Introduction This report seeks to detail the changes that the Borough Council of King’s Lynn and West Norfolk is proposing to mitigate the impact of developing on the south end of Southend Road carpark, and therefore help ensure a policy compliant and successful planning application.
2. Application 20/00811/FM Planning application 20/00811/FM was submitted by the Borough Council of King’s Lynn and West Norfolk in June 2020 seeking the construction of 32 apartments with associated access, cycle stores, infrastructure and landscaping. The original proposal was refused by the authority’s Planning Committee on the 8th December 2020 on two grounds:
1. The proposed development would result in the significant loss of 100 public car parking spaces, with would cause an adverse impact, especially during summer months, upon the ability to accommodate visitors to the town to the detriment of the local economy and amenity. The proposal is therefore considered to be contrary to the provision of Policy CS05 of the Core Strategy (2011) and the Hunstanton Town Centre & Southern Seafront Masterplan (2008).
2. The proposed development has inadequate parking provision within the application site to serve the number of dwellings sought. The proposal is therefore considered to be contrary to the provision of Policies DM15 & DM17 of the SADMPP (2016).
3. Proposed changes
3.1Additional onsite parking In response to concerns raised regarding the provision of onsite parking the Borough Council of King’s Lynn, in consultation with the project architects (The Design Partnership Ely Ltd) revised the site plan to (without altering the number of flats, the proposed site size, or further altering Southend Road carpark) add an additional 7 parking spaces to serve the buildings’ occupants and their visitors. This will lessen the burden that visitors to the development, may place on the 395 spaces that remain on Southend Road carpark.
This results in a total of 39 parking spaces on the development, which is 1.2 parking spaces per flat. This figure is in excess of other comparable developments recently approved within the town including:
a) Bus Station / Library Development – 20/00817/FM - 1 parking space per flat (with an additional 4 parking spaces to serve the library and retail unit) b) Land South of Seagate Hunstanton (Former Kit Kat site) - 19/01558/FM –17 Parking Space – 16 Flats – 1.06 parking spaces per flat (with no additional parking spaces to service the 3 retail units proposed 3
c) 19 - 21 Church Street (Whitney Press) - 20/00962/FM - 18 Parking Spaces – 18 Flats – 1 parking space per flat.
3.2Loss of 100 parking spaces The northern end of the Seagate East / southern end of the Hunstanton Coach park is poorly utilised and inefficiently laid-out, resulting in land that offers no usable parking spaces.
Previous consultation on the coach park, and whether this could be relocated out of town with convenient town centre drop-off points gained significant feedback that largely demonstrated that its current position meets the needs of local businesses and provides a safe a convenient location close to the seafront, with welfare facilities nearby for those using and operating the coaches. It therefore remains the council’s intention to retain the coach park in this location for the foreseeable future.
However, the current coach park has capacity for 19 coaches within lined spaces and further coaches within unlined areas of the coach park.
Usage of the site by coaches is more frequent in the core summer months (June, July, and August) during the week, especially during the period when schools send many pupils to the Sea Life centre and other seafront facilities. Conversely the coach park is more frequently used by the smaller motorhomes over the weekend, however significant capacity remains at these times.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies