CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Borough Council of King's Lynn and West Norfolk
Cabinet, Tuesday 16 March 2021 at 3.30pm

SOUTHEND ROAD, HUNSTANTON

Decided Executive 2 papers

Cabinet decided this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.

ItemCAB248

Resolved

RECOMMENDED: That the Council enters a contract with Lovell Partnerships Ltd under the Major Housing Contract to deliver this project, subject to planning permission being granted. Reason for Decision 1) To develop this site using the Major Housing contract with Lovell Partnerships Limited. 2) To allow the scheme to be developed using traditional methods. 3) To include the tenure mix shown in section 2.4 of this report.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Statement in response to Parking Loss at Southend Road – Hunstanton Prepared by: James Grant Property Services

January 2021 2

1. Introduction This report seeks to detail the changes that the Borough Council of King’s Lynn and West Norfolk is proposing to mitigate the impact of developing on the south end of Southend Road carpark, and therefore help ensure a policy compliant and successful planning application.

2. Application 20/00811/FM Planning application 20/00811/FM was submitted by the Borough Council of King’s Lynn and West Norfolk in June 2020 seeking the construction of 32 apartments with associated access, cycle stores, infrastructure and landscaping. The original proposal was refused by the authority’s Planning Committee on the 8th December 2020 on two grounds:

1. The proposed development would result in the significant loss of 100 public car parking spaces, with would cause an adverse impact, especially during summer months, upon the ability to accommodate visitors to the town to the detriment of the local economy and amenity. The proposal is therefore considered to be contrary to the provision of Policy CS05 of the Core Strategy (2011) and the Hunstanton Town Centre & Southern Seafront Masterplan (2008).

2. The proposed development has inadequate parking provision within the application site to serve the number of dwellings sought. The proposal is therefore considered to be contrary to the provision of Policies DM15 & DM17 of the SADMPP (2016).

3. Proposed changes

3.1Additional onsite parking In response to concerns raised regarding the provision of onsite parking the Borough Council of King’s Lynn, in consultation with the project architects (The Design Partnership Ely Ltd) revised the site plan to (without altering the number of flats, the proposed site size, or further altering Southend Road carpark) add an additional 7 parking spaces to serve the buildings’ occupants and their visitors. This will lessen the burden that visitors to the development, may place on the 395 spaces that remain on Southend Road carpark.

This results in a total of 39 parking spaces on the development, which is 1.2 parking spaces per flat. This figure is in excess of other comparable developments recently approved within the town including:

a) Bus Station / Library Development – 20/00817/FM - 1 parking space per flat (with an additional 4 parking spaces to serve the library and retail unit) b) Land South of Seagate Hunstanton (Former Kit Kat site) - 19/01558/FM –17 Parking Space – 16 Flats – 1.06 parking spaces per flat (with no additional parking spaces to service the 3 retail units proposed 3

c) 19 - 21 Church Street (Whitney Press) - 20/00962/FM - 18 Parking Spaces – 18 Flats – 1 parking space per flat.

3.2Loss of 100 parking spaces The northern end of the Seagate East / southern end of the Hunstanton Coach park is poorly utilised and inefficiently laid-out, resulting in land that offers no usable parking spaces.

Previous consultation on the coach park, and whether this could be relocated out of town with convenient town centre drop-off points gained significant feedback that largely demonstrated that its current position meets the needs of local businesses and provides a safe a convenient location close to the seafront, with welfare facilities nearby for those using and operating the coaches. It therefore remains the council’s intention to retain the coach park in this location for the foreseeable future.

However, the current coach park has capacity for 19 coaches within lined spaces and further coaches within unlined areas of the coach park.

Usage of the site by coaches is more frequent in the core summer months (June, July, and August) during the week, especially during the period when schools send many pupils to the Sea Life centre and other seafront facilities. Conversely the coach park is more frequently used by the smaller motorhomes over the weekend, however significant capacity remains at these times.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hunstanton Southend Road: Statement in support of Parking Loss Rev 3Report 3.1 MB DownloadRead as text
PDF
SOUTHEND ROAD, HUNSTANTONReport 470 KB Download

At this meeting

Whole meeting

Who was there

7 of 18 attended
AB
Alexa BakerOfficer, expected
KB
Kate BlakemoreOfficer, expected
RB
Councillor Richard BluntCommittee Member, present
JC
Jemma CurtisCouncil Staff, expected
SD
Councillor Stuart DarkCommittee Member, apologies
MD
Michelle DreweryOfficer, expected
ED
Emma DuncanOfficer, expected
DG
Debbie GatesOfficer, expected
PG
Councillor Peter GidneyCommittee Member, present
LG
Lorraine GoreOfficer, expected
GH
Geoff HallOfficer, expected
AI
Aaron IrelandCouncil Staff, expected

All 18 on the meeting page

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies