REPORT TO: Corporate Performance Panel DATE: 21 July 2021 TITLE: Corporate performance monitoring update – Interim report TYPE OF REPORT: Monitoring PORTFOLIO(S): Performance REPORT AUTHOR: Honor Howell OPEN/EXEMPT Open WILL BE SUBJECT No TO A FUTURE CABINET REPORT:
REPORT SUMMARY/COVER PAGE
PURPOSE OF REPORT/SUMMARY: At the Corporate Performance Panel meeting held on 2 June 2021, the panel requested an interim report focusing on the performance indicators where performance was worse than the previous year as at the 31 March 2021.
KEY ISSUES: These indicators are linked to the Covid-19 Recovery Strategy and are grouped under the Corporate Business Plan’s priorities. The Corporate Performance Panel monitors all indicators to provide a corporate overview of performance.
Members will be aware that the council’s response to Covid-19 continued throughout 2020/21 and was ramped up in response to national measures and preparations for the vaccination programme. Resources were refocused from recovery to concentrate on response activities and indicators that are heavily influenced by external factors were anticipated to deteriorate over quarters 3 and 4 of 2020/21 and into 2021/22 subject to the lifting of national restrictions and the related impact of national and local economic recovery.
OPTIONS CONSIDERED: Not applicable as this is a monitoring report.
RECOMMENDATIONS: The Panel is asked to review and note the report.
REASONS FOR RECOMMENDATIONS: Members should use the information within the report to review progress on the agreed indicators and satisfy themselves that performance is at an acceptable level. 1. Introduction
1.1The council monitors a range of indicators from across directorates as a form of corporate assurance, to demonstrate efforts to continuously improve services and to track progress with the Covid-19 Recovery Strategy.
1.2Processes are put in place to produce the required information by relevant services, and the information is then collated and analysed centrally by the Performance team.
1.3The collated information is used to produce an overarching report which is presented to the Corporate Performance Panel and is made available to all councillors for information on the council’s intranet known as Insite.
2. Performance indicators where performance was worse than the previous year as at the 31 March 2021
2.1Priority 1 – Focus on delivery
i) % of Council Tax collected against target
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 98% 97% 9% 19% 10% 19%
2.2Priority 2 – Delivering growth in the economy and with local housing
i) Job seekers allowance claimant rate
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 278 441 489 525 369 282
ii) No in employment claiming Universal Credit
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 1,888 4,380 2,881 3,578 4,453 To follow
iii) % of rent arrears on industrial units
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 5.50% 17.78% 10.78% 11.25% 17.69% 17.57%
iv) % of rent arrears on retail/general units
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 6.28% 32.87% 8.95% 16.58% 36.33% 34.39%
v) Number of new homes delivered
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 591 340 14 8 43 30 vi) % of decisions on applications for non-major development that have been overturned at appeal, measured against total number of non-major applications determined
End of Year End of Year April May April May 2019/20 2020/21 2020/21 2020/21 2021/22 2021/22 0.61% 0.69% 0.71% 0.59% 0.60% 0.67%
2.3Priority 3 – Protecting and enhancing the environment including tackling climate change
i) Total tonnage of waste recycled and composted
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Performance Monitoring Update: Interim ReportReport | 299 KB | DownloadRead as text |
Follow Corporate Performance Panel at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Appointment of Vice - Chair for the MeetingCouncillor Spikings was appointed Vice – Chair for the meeting. | Decided | Open |
| 10 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Corporate Performance Monitoring Quarter 2The Panel supported the recommendations to Cabinet. Cabinet Resolves to: 1. To review the Performance Management Repo... | Decided | Open |
| 10 Nov 2026 | Cabinet Report – Council Tax Support Scheme for Working Age People for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: That the draft Counc... | Agreed | Open |
| 10 Nov 2026 | Cabinet Report - Council Tax Discounts, Levies and Premiums for Empty Properties and Second Homes for 2027/2028The Panel supported the recommendations to Cabinet then Council. Recommendation to Full Council: The following discou... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.