Resolved
That the recommendations above from the Cabinet meeting on 8 February 2023 be approved.
Council approved this item on Thursday 9 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the recommendations above from the Cabinet meeting on 8 February 2023 be approved.
RECOMMENDATIONS FROM CABINET ON 8 FEBRUARY 2023 TO COUNCIL ON 23 FEBRUARY 2023
CAB129 HUNSTANTON MULTI USER HUB AND TRANSPORT INTERCHANGE
Click here to view the recording of this item on You Tube
R Eacott, Interim Project Delivery and Technical Advisor presented the report which explained that a planning application to build 47 apartments on land off Westgate, Hunstanton, with retail units, a new library and adult education facility, was approved in March 2021.
Work to develop this proposal, which would have provided a significant number of new homes for the town on a challenging site, was supported with a grant from Homes England. Around £800,000 was spent on this work, which was significantly less than the £1.5million that would be normal for a scheme of this size (figure based on 15% of a £10.4m scheme).
At the time that the planning application was submitted, Document B (Fire Safety) Volume 1, stipulated a height threshold of 30m before residential buildings required sprinklers. The proposed building would have been below this height. However, changes to Building Regulations (Approved Document B, Volume 11) were published in May 2020, taking effect from November 2020; the revised guidance stated that blocks of flats over 11m height should be provided with sprinklers. The top floor of the proposed unit was over 11m. At the time, officers felt that it would be possible to proceed with the application and seek a way to resolve the sprinkler issue retrospectively. However, a month after permission was granted, further regulatory changes – this time to fire standards – were announced. This, combined with unforeseen rises in construction costs following the Covid-19 pandemic, and more recently forecast falling house prices, has had a material impact on the financial viability of this scheme, and to other Borough Council Major Housing Projects within the Capital Programme.
Officers had therefore been considering alternative options for the site. Matters of note have influenced that thinking: 1. A Neighbourhood Plan for Hunstanton was adopted in June 2022. This plan identified the designation of the site in the Neighbourhood Plan (Policy M3: Protection of Local Community Facilities). 2. The County Council had indicated funding was available that could be used to support a plan to invest in an improved library / adult education facility (with toilets and a changing place facility), along with investment in an improved bus station and creating an Active Travel Hub. 3. The impact of financial viability of the housing development on the overall Accelerated Construction Programme (ACP). Having reached the conclusion that the site had become unviable for a variety of reasons as a location for housing, the availability of other government grant for transport, and NCC prepared to fund their own library and to invest in the site as an Active Travel Hub, officers instead recommended that the Council pursues this option.
Under standing order 34, Councillor de Whalley confirmed that Hunstanton was in need of investment and this would help to redress the balance.
Under standing order 34, Councillor Parish confirmed he was not against this proposal but suggested that Heacham library be funded by the County Council.
Under standing order 34, Councillor Joyce made comments about west Norfolk not previously getting County Council funding.
Under standing order 34, Councillor Dickinson asked if it was being done with existing planning permission or new and the timescale proposed.
It was confirmed that a new planning application would be required on the same footprint, and with changes to the layout of the bus station. It was hoped to start in 2023.
Councillor Blunt expressed disappointment that the original plan was not viable, but embraced the amended proposals which were a sign of better working relationships with the County Council. He hoped it could be delivered swiftly.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Recommendations from Council Bodies: Cabinet 8 February 2023Report | 142 KB | DownloadRead as text |
Follow Council at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | MINUTESThe minutes from the meeting held on 24 th September 2026 were agreed as a correct record. | Agreed | Open |
| 29 Oct 2026 | Appointment of honorary alderman and presentation of the engrossments of the resolution and badge of officeThat the title of Honorary Alderman was conferred on former Councillors Carol Bower, Colin Manning, Lesley Bambridge ... | Decided | Open |
| 24 Sep 2026 | MINUTESThe minutes from the meeting held on 29 th July were agreed as a correct record. | Agreed | Open |
| 24 Sep 2026 | Review of proportionalityThat the Membership of the Audit Committee be increased from five Members to Seven Members. 2. That the proportional ... | Decided | Open |
| 24 Sep 2026 | Recommendations from council bodiesThat the Council places on record its sincere appreciation and gratitude for the eminent services rendered to the Bor... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.