AI summaryCouncil approves £845,609.17 from reserves to design a replacement swimming pool at Lynnsport, with a final go-or-no-go decision expected in March 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTo progress new Lynnsport pool to RIBA Stage 3
Money£845,609.17 from reserves3.7% of estimated £22.93 million total project cost
What happens nextFinal decision expected March 2027Anticipated completion by March 2029 if approved
Who it affectsWest Norfolk residents and school childrenParticularly those learning to swim and water safety
What was decided
Council approved a maximum of £845,609.17 from reserves to fund the new Lynnsport swimming pool project through to RIBA Stage 3, producing a final design, cost-certainty and business case. Report P23, P25
Authority was delegated to the Section 151 Officer, in consultation with the Leader and the Finance Portfolio Holder, to choose which reserve to draw the money from. Report P24
The meeting also placed on record appreciation for four former councillors and moved to confer on them the title of Honorary Alderman under Section 249(1) of the Local Government Act 1972. Report P1
Why
St James Swimming Pool is ageing, near the end of its operational life, increasingly costly to maintain and posing a growing risk to continuity of swimming provision. Report P7, P26
The £845,609.17 represents 3.7% of the estimated total project cost of £22.93 million, with 6% to 10% typically needed to reach this design stage, and covers design work, ground investigations, business case preparation and professional services. Report P10, P18
A 2024 survey found drowning levels had doubled, over 200 water-related incidents occurred in the previous year and 22 people drowned in Norfolk over the preceding five years, with more than one million pupils due to enter secondary education in 2026 unable to swim or stay safe in water. Report P12
What happens next
Project to progress to RIBA Stage 3 to produce the detailed design and business case. Report P23, P25
A final decision on whether to proceed with construction is expected to go to Cabinet and Council in March 2027. Report P16
If approved, completion of the new standalone pool at Lynnsport is anticipated by March 2029, with St James Swimming Pool expected to remain operational until the new facility is ready. Report P15, P16
The money
£845,609.17 Maximum allocation from reserves to fund the new Lynnsport project through to RIBA Stage 3 Report P23
£22.93 million Estimated total cost of the swimming pool project Report P18
Options considered
Chosen: Replace St James Swimming Pool with a standalone facility at Lynnsport. Enables continuity of service; Lynnsport identified as the preferred location Report P6, P15
Implications
Financial: Up to £845,609.17 will be drawn from reserves, with the specific reserve to be chosen by the Section 151 Officer in consultation with the Leader and Finance Portfolio Holder. Report P23, P24
Risk: St James Swimming Pool is continuing to deteriorate, with rising maintenance requirements and operating costs creating a growing risk to the continuity of swimming provision. Report P26
Equalities: The proposals are framed within the Marmot approach, with a focus on improving water literacy in deprived communities. Report P17
Other: Following the pause in Local Government Reorganisation, any future decision on whether to proceed will likely rest solely with the Borough Council. Report P8
Legal: The Honorary Alderman title is conferred under Section 249(1) of the Local Government Act 1972.
Who and where
Residents of King's Lynn and West Norfolk who use swimming facilities Report P7, P14
School children, including the more than one million pupils nationally due to enter secondary education in 2026 who cannot swim or stay safe in water Report P12
Users of the proposed movable pool floor, which is intended to improve accessibility and programming flexibility Report P20
Timeline
2026-09-24: Council considers the Cabinet recommendation to allocate funding to progress the Lynnsport pool to RIBA Stage 3
March 2027: Final go-or-no-go decision on the project expected to be presented to Cabinet and Council Report P16
March 2029: Anticipated completion of the new swimming pool at Lynnsport if the project proceeds Report P16
Plain English for the jargon
RIBA Stage 3: The third stage of the Royal Institute of British Architects' plan of work, covering developed design and producing detailed design information.
Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of its financial affairs.
Marmot approach: A public health approach based on the work of Sir Michael Marmot, focused on reducing health inequalities and the social determinants of health.
Honorary Alderman: A title that a council may confer on a former councillor under Section 249 of the Local Government Act 1972 in recognition of eminent service.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC:44
Resolved
That the Council places on record its sincere appreciation and gratitude for the eminent services rendered to the Borough Council by former Councillors Carol Bower, Colin Manning, Lesley Bambridge and Lord Greville Howard. 2. That, pursuant to Section 249(1) of the Local Government Act 1972, the title of ... view the full minutes text for item C:44
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
To formally recognise and record the Council’s appreciation of the service of the former Borough Councillors listed above through the conferment of the title of Honorary Alderman and the holding of an Extraordinary Council meeting for that purpose.
CAB46 FUTURE SWIMMING PROVISION FOR WEST NORFOLK
Click here to view the recording of this item on You Tube.
The Monitoring Officer advised Cabinet that the report was being considered in open session. However, she noted that a separate report contained exempt information and that, should Cabinet wish to discuss any of the exempt elements, it would be necessary to temporarily exclude the press and public from the meeting.
Councillor Beales proposed amendments to the recommendations, namely that the allocation of £845,609.17 should be approved as the maximum amount and that the Leader should be consulted in relation to the exercise of the delegated authority proposed for the Chief Operating Officer and the Section 151 Officer. Cabinet agreed to the amended recommendations.
The Strategic Adviser to the Chief Executive and Leader presented the report and outlined the preferred option for replacing St James Swimming Pool with a standalone facility at Lynnsport. Cabinet was informed that approval was sought to progress the project to RIBA Stage 3, at which point a detailed business case would be available and a further decision would be required regarding whether the project should proceed.
The Strategic Adviser provided an overview of the current position at St James Swimming Pool, explaining that the facility was ageing, approaching the end of its operational life and becoming increasingly costly to maintain.
Cabinet noted that, following the pause in Local Government Reorganisation, any future decision on whether to proceed with the project would likely rest solely with the Borough Council.
Councillor Rust referred to the potential public perception of the costs involved, noting that the sum requested related solely to progressing the project to RIBA Stage 3. She also highlighted the importance of maintaining swimming provision to improve water literacy and ensure that residents and communities had opportunities to learn to swim and develop water safety skills.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.